The project ______ is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.
A、
work performance information
B、
scope statement
C、
change requests
D、
process analysis
【正确答案】
B