单选题

A company entered into a three-year construction project with a total contract price (all figures in '000s) of $5,300 and expected costs of $4,400. The company recognizes revenue using the percentage of completion method. The data below relate to the contract.

【正确答案】 B
【答案解析】

B is correct.