结构推理 Within 7 days after signing the contract of this construction project by both parties, Party B shall pay to Party A a performance deposit amounting to 10/% of the total project cost, or provide an irrevocable bank surety payable at sight.The deposit or surety shall be refunded without interest to Party B after completion of the project.
【正确答案】本工程合同经双方签字后7天内,由乙方按工程总费用的10/%交付履约保证金,或提供即期的不可撤销的银行担保,工程结束后由甲方无息退还乙方。
【答案解析】