| {{B}}表4-28清单工程量计算 工程名称:接待室工程{{/B}} | |||||
| 序号 | 项目编码 | 项目名称 | 单位 | 工程数量 | 计算式 |
| 1 | 010101001001 | 平整场地 | m2 | 51.56 | (5.0+0.24)×(3.60+3.30+2.70+0.24) |
| 2 | 010101003001 | 人工挖基础土方 (墙基) |
m3 | 34.18 | [(5.0+9.6)×2+(5.0-0.8)+ (3.0-0.8)]×0.8×1.2 |
| 3 | 010101003002 | 人工挖基础土方 (柱基) |
m3 | 0.77 | 0.8×0.8×1.2 |
| 4 | 010301001001 | M5水泥砂浆砌砖 基础 |
m3 | 15.08 | (29.20+5.0-0.24+3.0-0.24)× [(1.50-0.20)×0.24+0.007875×12]+ [(0.24+0.0625×4)×(0.24+0.0625×4)+ (0.24+0.0625×2)×(0.24+0.0625×2)]× 0.126×2+(1.50-0.20-0.126×2)× 0.24×0.24 |
| 5 | 010103001001 | 人工基础回填土 | m3 | 22.53 | 34.18+0.77-15.08+36.72×0.24×0.30+ 0.30×0.24×0.24 |
| 6 | 010103001002 | 人工室内回填土 | m3 | 8.11 | (51.56-36.72×0.24-0.24×0.24)× (0.30-0.08-0.02-0.01) |
| 7 | 010302001001 | M5混合砂浆砌 砖墙 |
m3 | 24.76 | (36.72×3.60-0.9×2.40×4-1.50×1.50× 6-1.10×1.501×0.24-29.20×0.18×0.24 |
| 8 | 010302005001 | M5混合砂浆砌 砖柱 |
m3 | 0.21 | 0.24×0.24×3.60 |
| 9 | 010403002001 | 现浇C20混凝土 矩形梁 |
m3 | 0.36 | (2.70+0.12+2.0+0.12)×0.24×0.30 |
| 10 | 010403004001 | 现浇C20混凝土 圈梁 |
m3 | 1.26 | 29.20×0.18×0.24 |
| 11 | 0 10407002001 | 混凝土散水 | m2 | 22.63 | (29.20+0.24×4)×0.80-(2.7-0.12+ 0.12+0.3+2.0-0.12+0.12)×0.30 |