单选题
Project work packages are typically decomposed into smaller components called activities to provide a basis for ______, scheduling, executing, and monitoring and controlling the project work.
A.reviewing B.estimating C.auditing D.expecting
A
B
C
D
【正确答案】
B
【答案解析】