单选题
JME Construction always uses the percentage of completion method of recognizing revenue. During 2004 JME signs a contract in the amount of $10 million with the following data available:
【正确答案】
A
【答案解析】stage of completion = 25 % (2.2/8.8)
revenue to be recognized =0.25×10 million =2.5 million
gross profit = 2.5 million-2.2million=300000