单选题
Which of the following is not part of a modern quality management concept? ______
A、
Performance standard is zero defects
B、
Quality must be inspected in
C、
85% of failures occur because of the process, not the worker
D、
Quality is a 4 cycle process - plan/do/check/act
【正确答案】
B
【答案解析】