序号 | 项目编码 | 项目名称 | 单位 | 工程数量 | 计 算 式 |
1 | 010101001001 | 平整场地 | m2 | 51.56 | (5.0+0.24)×(3.60+3.30+2.70+0.24) |
2 | 010101003001 | 人工挖基础土方(墙基) | m3 | 34.18 | [(5.0+9.6)×2+(5.0-0.8)+(3.0-0.8)]×0.8×1.2 |
3 | 010101003002 | 人工挖基础土方(柱基) | m3 | 0.77 | 0.8×0.8×1.2 |
4 | 010301001001 | M5水泥砂浆砌砖基础 | m3 | 15.08 | (29.20+5.0-0.24+3.0-0.24)×[(1.50- 0.20)×0.24+0.007875×12]+[(0.24+0.0625 ×4)×(0.24+0.0625×4)+(0.24+0.0625× 2)×(0.24+0.0625×2)]×0.126×2+(1.50 -0.20-0.126×2)×0.24×0.24 |
5 | 010103001001 | 人工基础回填土 | m3 | 22.53 | 34.18+0.77-5.08+36.72×0.24×0.30+0.30 ×0.24×0.24 |
6 | 010103001002 | 人工室内回填土 | m3 | 8.11 | (51.56-36.72×0.24-0.24×0.24)×(0.30 -0.08-0.02-0.01) |
7 | 010302001001 | M5混合砂浆砌砖墙 | m3 | 24.91 | (36.72×3.60-0.9×2.40×4-1.50×1.50×6-1.10×1.50)×0.24-29.20×0.18×0.24 |
8 | 010302005001 | M5混合砂浆砌砖柱 | m3 | 0.19 | 0.24×0.24×3.30 |
9 | 010403002001 | 现浇C20混凝土矩形梁 | m3 | 0.36 | (2.70+0.12+2.0+0.12)×0.24×0.30 |
10 | 010403004001 | 现浇C20混凝土圈梁 | m3 | 1.26 | 29.20×0.18×0.24 |
11 | 010407002001 | 混凝土散水 | m2 | 22.63 | (29.20+0.24×4)×0.80-(2.7-0.12+0.12+0.3+2.0-0.12+0.12)×0.30 |