单选题 Which of the following is true about the WBS:
  • A) The WBS is another term for the Gantt chart.
  • B) Each descending level of the WBS represents an increasingly detailed definition of the project work.
  • C) Work not in the WBS is usually defined in the scope statement of the project.
  • D) The WBS shows only the critical path activities.


【正确答案】 B
【答案解析】[解析] 下列哪项关于WBS的说法是正确的?
A) WBS是甘特图的另外一种术语。
B) WBS中越是向下的层次所描述的项目工作越是详细。
C) 没有在WBS中的工作通常定义在项目范围说明中。
D) WBS只显示关键路径的活动。
WBS的特点是:分层显示项目的可交付成果和工作,越是底层显示的项目工作越详细。