单选题
An analyst does research about revenue recognition andgathers the following information about a construction contract with outcome that can be reliably measured: ·Estimated total revenues to be collected is $250000 ·Estimated total costs to be incurred is $175000 ·Cash collected during year 1 is $100000 ·Costs incurred during year l is $ 80 000 Assuming the project will be completed after 4 years, the revenue from the contract recognized for year 1 is closest to? A. $0 B. $142857 C. $114285