单选题
The earned value technique is a commonly used method of performance measurement. It integrates project scope, schedule, and cost measures to help the project management team assess project performance. If a project's Cost Performance Index (CPI=EV/AC) value less than 1.0, it means that ______. A. the cost savings for work completed B. the project is ahead of its planned schedule C. the cost overrun for work completed D. less work was completed than was planned