选择题 71.  ______ techniques are used to find ways to bring projiecl activities that are alignment with the plan by fast tracking or crashing the schedule for the remaining work.
【正确答案】 B
【答案解析】 翻译:______技术用于通过快速跟踪或破坏剩余工作的计划来找到使落后的项目活动与计划保持一致的方法。
   A.进度预测    B.进度压缩    C.变更请求    D.数据分析