[问题]| 序号 | 项目编码 | 项目名称 | 计量 单位 | 工程 数量 | 计算公式 |
| 1 | 010101001001 | 平整场,二类土,5m运距 | |||
| 2 | 010402001001 | 矩形框架柱,截面尺寸:0.4m×0.3m, H=11.03m.C25砾40 | |||
| 3 | 010402001002 | 矩形独立柱,截面尺寸:截面尺寸:0.3m×0.3m, H=4.22m.C25砾40 | |||
| 4 | 010402001003 | 构造柱,三边有墙,截面尺寸:0.24m×0.24m, H=11.03~13.31m,C25砾40 | |||
| 5 | 010402001004 | 构造柱,三边有墙,截面尺寸:0.24m×0.24m, H=11.03~13.31m,C25砾40 | |||
| 6 | 010405001001 | 有梁板,二层,板厚0.1m,板底标高3.36m, C20砾40 | |||
| 7 | 010405001002 | 有梁板,二层,板厚0.1m,板底标高7.06m, C20砾40 | |||
| 8 | 010405001003 | 有梁板屋面,板厚0.1m,板底标高10.37m, C20砾40 | |||
| 9 | 010405003001 | 平板,二层7~8轴/A~D轴,板厚0.1m,板底 标高3.36m,C20砾40 | |||
| 10 | 020105003001 | 块料踢脚线,高150mm,厚17mm, 2:1:8水泥石灰砂浆,3~4mm,厚1:1 水泥砂浆加20%108胶 | |||
| 11 | 020106002001 | 块料楼梯面层,20mm厚1:3水泥砂浆,0.4m× 0.4m×0.1面砖 | |||
| 序号 | 项目编码 | 项目名称 | 计量 单位 | 工程 数量 | 计算公式 | |||||
| 1 | 010101001001 | 平整场,二类土,5m运距 | m2 | 150 | (11.76+0.24)×(12.26+0.24)=150 | |||||
| 2 | 010402001001 | 矩形框架柱,截面尺寸:0.4m×0.3m, H=11.03m.C25砾40 | m3 | 5.29 | 现浇钢筋混凝土框架柱,周长1.80m内,C25: KJ-1:0.40×0.30×(10.38+1.20±0.00以下 -0.10垫层-0.45基础)×4个=5.29 ±0.01以下:0.40×0.30×(1.20-0.10 -0.45)×4个=0.31 室外地坪以下:0.40×0.30×0.20×4=0.10? | |||||
| 3 | 010402001002 | 矩形独立柱,截面尺寸:截面尺寸:0.3m×0.3m, H=4.22m.C25砾40 | m3 | 1.52 | 现浇钢筋混凝土独立柱,周长1.20m以内,C25: Z-1:0.30×0.30×(3.57+1.20±0.00±0.00以下 -0.10垫层=0.451×4个=1.52 ±0.01以下:0.30×0.30×(1.20-0.10 -0.45×4个=0.23 室外地坪以下:0.30×0.30×0.20×4=0.07? | |||||
| 4 | 010402001003 | 构造柱,三边有墙,截面尺寸:0.24m×0.24m, H=11.03~13.31m,C25砾40 | m3 | 5.06 | 两边有墙: 1轴交C轴,8轴交A、G轴(-0.65~12.66), 3根: [0.24×0.24×(12.66+0.65)+0.24×0.06 ×2边×(12.66+0.65)×0.5马牙搓×3个=2.88 1轴交A轴,2轴交C轴(-0.65~10.37m), 2根: [0.24×0.24×(11.70-10.73)+0.24×0.06 ×2边×(10.37+0.65)×0.5马牙搓×2个=1.58 1轴交D轴,8轴交D轴,2根,10.37~11.70m 两边有墙: [0.24×0.24×(11.70-10.37)+0.24×0.06 ×2边×(11.70-10.37)×0.5马牙搓×2个 =0.20 7轴交A轴,1根,7.17~12.66m两边有墙: 0.24×0.24×(12.66-7.17)+0.24×0.06 ×2边×(12.66-7.17)×0.5马牙搓=0.40 构造柱两边有墙合计:2.88+1.58+0.20 +0.40=5.06? | |||||
| 5 | 010402001004 | 构造柱,三边有墙,截面尺寸:0.24m×0.24m, H=11.03~13.31m,C25砾40 | m3 | 3.23 | 三边有墙: 1轴交D轴,8轴交D轴,2根,-0.65~ 10.37m三边有墙: [0.24×0.24×(10.37+0.65)+0.24×0.06 ×3边×(10.37+0.65)×0.5马牙搓1×2个=1.74 7轴交A轴,l根,-0.65~7.17m三边有墙:? 0.24×0.24×(7.17+0.65)+0.24×0.06 ×3边×(7.17+0.65)×0.5[马牙搓=0.62 2轴交A轴-0.65~10.37m,1根: 0.24×0.24×(10.37+0.65)+0.24 ×0.06×3边×(10.37+0.65)×0.5马牙搓=0.87 构造柱三边有墙合计:1.74+0.62+0.87 =3.23? | |||||
| 6 | 010405001001 | 有梁板,二层,板厚0.1m,板底标高3.36m, C20砾40 | m3 | 15.04 | B1:2~5轴交A~C轴 (2.40-0.24)×(1.50+2.30-0.24) ×0.08=0.62 L-1: (1.50-0.15÷2-0.24÷2)×0.15 ×(0.40-0.08)=0.06 L-2: (2.40-0.24)×0.15×(0.40 -0.08)=0.10 LL-1a: (11.76-0.25LL-2-0.3×2Z-1)×0.25×(0.40-0.10)=0.80 LL-1b:(11.76-0.18×2Z-1-0.25×2KJ-1)×0.25×(0.35-0.10)×2根=1.36 LL-1: (7.10-0.25LL-1a-0.30×2Z-1)×0.25×(0.30-0.10)×2根=0.63 KJ-1:(7.10-0.125×2)×0.25×(0.60 -0.10×2根=1.71 YPL: (11.76-0.25-0.30×2Z-1)×0.25 ×(0.45-0.10)=0.95 二层小计:8.81+0.62+0.06+0.10+0.80 +1.36+0.63+1.71+0.95=15.04 | |||||
| 7 | 010405001002 | 有梁板,二层,板厚0.1m,板底标高7.06m, C20砾40 | m3 | 0.79 | 三层: B2:2~5轴交A~C轴 (2.40-0.24)×(1.50+2.30-0.24) ×0.08=0.62 L-1: (1.50-0.15÷2)×0.15×(0.40 -0.081=0.07 L-2: (2.40-0.24)×0.15×(0.40 -0.081=0.10 三层小计:0.62+0.07+0.10=0.79 | |||||
| 8 | 010405001003 | 有梁板屋面,板厚0.1m,板底标高10.37m, C20砾40 | m3 | 2.97 | 屋面: 板:2~5轴交A~C轴 (5.16-0.24-1.36)×(3.40+3.36 -0.241×0.10=2.32 TCL-2: (3.40+3.36+0.24)×0.24×(0.30-0.10)=0.34 L-4:(5.16-0.24-1.36)×0.25×(0.45 -0.10)=0.31 屋面小计:2.32+0.34+0.31=2.97 | |||||
| 9 | 010405003001 | 平板,二层7~8轴/A~D轴,板厚0.1m,板底 标高3.36m,C20砾40 | m2 | 1.53 | 现浇钢筋混凝土平板,10cm以内,C20 二层:7~8轴交A~D轴 (5.16-0.24÷2-0.25÷2)×(3.36 -0.24)×0.10=1.53 | |||||
| 10 | 020105003001 | 块料踢脚线,高150mm,厚17mm, 2:1:8水泥石灰砂浆,3~4mm,厚1:1 水泥砂浆加20%108胶 | m2 | 48.46 | 陶瓷地砖路踢脚,高150cm,98ZJ001,23/24 一层: 仓库(2): [(3.36-0.24+5.16-0.24) ×2-1.00M2×0.15=2.26 仓库(1): [(3.40-0.24+5.16-0.24) ×2+(0.40-0.24)×2KJ-1-1.00×2M2 ×0.15=16.18 走廊2~5: [(2.40-0.12)D轴+(2.40 -0.12+0.12)C轴+(1.36-0.24)5轴+(0.40 -0.24)×2KJ-1-1.00M2-0.8M3×0.15 =0.65 梯间:斜道长为: [2.40Z+(2.40/8)21/2 =2.42(m) [(2.60-0.12D轴+5.16-0.24-2.4斜道水平长 +2.42斜道长+(2.60-0.24)A轴+(3.80 -0.12-2.40+2.42)2轴-1.00MZ]-1.00M4×0.15=1.72 一层小计:2.26+16.18+0.65+1.72=20.81 二层: 工作室(1): [(11.76-0.24+7.10 -0.24)×2-1.00×2M21×0.15=5.21 工作室(2):2.26m2[同一层仓库(2)] 会计室:[(3.40-0.24+5.16-0.24)×2 +(0.40-0.24)×2KJ-1-1.00M2 ×0.15=2.32 走廊2~5:0.65m2(同一层走廊) 梯间:(尺寸见1—1剖面图) [(1.24-0.12+2.70×1.37梯级+1.22 -0.12+2.60-0.24)×2-(1.36-0.12)走廊 -1.00M2×0.15=2.15 二层小计:5.21+2.26+2.32+0.65+2.15 =12.59 三层: 办公室:[(7.10-0.24+4.00-0.24)×2 -1.00M2×0.15=3.04 卧室(1): [(3.76-0.24+5.60-0.24) ×1.00M2×0.15=1.33 卧室(2): [(4.00-0.24+5.60-0.24) ×2-1.00×2m2×0.15=2.44 客厅:[(5.16-0.24+3.40+3.36-0.24) ×2-1.00×3M2-0.08M3×0.15=2.97 走廊2~5:0.65m2(同一层走廊) 梯间:2.15m2(同二层梯间) 阳台:[(3.76+4.00-0.24+1.50 -0.24)×2-1.00M2×0.15=2.48 三层小计:3.04+1.33+2.44+2.97+0.65 +2.15+2.48=15.06 陶瓷地砖路踢脚合计:20.81+12.59 +15.06=48.46 | |||||
| 11 | 020106002001 | 块料楼梯面层,20mm厚1:3水泥砂浆,0.4m× 0.4m×0.1面砖 | m2 | 17.94 | 楼梯防滑面砖: (2.70+1.22-0.12)×(2.60-0.24) ×2层=17.94 | |||||