Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. ______ is following the process - Estimate Activity Durations.
A、
Develop Schedule
B、
Estimate Activity Resources
C、
Define Activities
D、
Sequence Activities
【正确答案】
A