单选题
In the process of communication requirement analysis, the project
manager should consider the number of potential communication channels or paths
as an indicator of the complexity of a project's communication. According to
Metcalfe's Law, a project with 10 stakeholders. has ______ potential
communication channels.
单选题
Your company CEO just sent you an E-mail asking you to make a
presentation on your project, which has been in progress for 10 months, to all
Identified internal and external stakeholders. He scheduled the presentation for
next Monday. You expect more than 50 people to attenD. The first step in
preparing the presentation is to ______。
单选题
The communication management plan determines the information and
communications needs of the stakeholders. In the following statements related to
communication management plan. ______ is false.
A.The communication management plan is contained in or is a subsidiary plan
of, the project management plan.
B.The communication management plan can be formal or informal, highly
detailed or broadly framed, and based on the needs of the project.
C.The communication management plan organize and summarize the information
gathered, and present the results of any analysis as compared the performance
measurement baseline.
D.The communication management plan can include guidelines of project status
meetings, project team meetings, e-meetings, and e-mail.
【正确答案】
C
【答案解析】[解析] C错,C选项说的是项目绩效报告。
单选题
Stakeholder management refers to managing communications to satisfy
needs of, and resolve issues with project stakeholders. The ______ is usually
responsible for stakeholder management.