单选题 As part of monitoring and controlling, project performance must be monitored and measured regularly to identify variances from the plan. All the following are processes involved with controlling EXCEPT______.
A) verify scope B) risk monitoring and control
C) performance reporting D) quality assurance

【正确答案】 D
【答案解析】[解析] 作为监视和控制的一部分, 必须根据计划对项目绩效进行有规律的监视和测量。
下列所有都属于控制过程, 除了______。
A) 核实范围 B) 风险监视与控制
C) 绩效报告 D) 质量保证
质量保证属于执行过程组。