单选题
The ( ) process ascertains which risks have the potential of affecting the project and documenting the risks' characterist.
A、
Risk Identification
B、
Quantitative Risk Analysis
C、
Qualitative Risk Analysis
D、
Risk Monitoring and Control
【正确答案】
A
【答案解析】