单选题Due to lack of employee training and proper production controls, defects in a production run caused rework which cost the company $ 250000. How much of this cost is directly attributable to the employees on the production line? A) $75OOO B) $37500 C) $212500 D) $145OO
单选题While working on an external project your customer asks you to perform some additional tasks that are not included in the formal contract.You should______.
单选题If Task B has 15 days of free float and 25 days of total float, and the early start date of Task B is delayed 30 days, how is the project affected? A) The next dependent task's start date will be delayed 15 days. B) The duration of the task will be shortened 15 days. C) The completion date of the project will be pushed out 5 days. D) Both A and C.
单选题你负责一个穿过城镇的省级公路项目,该项目涉及沿路周边的居民的利益。虽然政府已经就某些补偿和居民达成了一致,但是为了确保项目顺利进行,项目经理还应该______。
单选题The expected time TE used in the PERT algorithm is calculated using the following equation ______. A) (a+3m+b)/6 B) (a+4m+b))/6 C) (a+5m+b)/6 D) (a+m+b)/3 Note: A major assumption for all network methods is that activity durations are statistically dependent and where a=most optimistic time, b=most pessimistic time, m=most likely time.
单选题 某个新产品研发项目,预计投资200万美元。该产品未来市场前景很好的概率为50%
单选题Verify scope ______ . A) is the process of obtaining the stakeholders formal acceptance of the completed project scope and associated deliverables B) refers to the final project report describing the project at completion C) is not necessary if the project completes on time and on budget D) OCCURS only when revisions of change orders are made to the project
单选题 风险概率影响矩阵______。
单选题Which type of input is the primary cause of contract changes? A) Independent estimates. B) Organizational policies. C) Statement of work. D) Approved changes requests.
单选题An output of scope definition is ______ .
单选题在规划质量过程中,项目经理需要确定将来用于检查质量的目标值、控制界限、规格界限以及进行质量检查的频率。他应该使用以下哪个工具与技术?( )A.控制图B.标杆对照C.流程图D.实验设计
单选题合同奖励条款是用来做什么的?
单选题When checking the calendar of a team member to schedule a meeting,you see she has scheduled a meeting with a key stakeholder that you were not informed of.The BEST approach would be to______.
单选题在项目计划编制阶段的早期,项目经理应该使用哪种领导风格?( ) A.教练型 B.指挥型 C.支持型 D.授权型
单选题用干系人分析技术,已经识别出了项目的所有干系人及其信息,下一步应该做什么?______
单选题Tools and techniques for performance reporting include all of the following EXCEPT:
单选题下列对概率影响矩阵的描述中,最好的是______。
单选题 组织内各项目的竞争非常激励,多个项目都向职能经理申请了技术人员
单选题在风险应对规划过程中,团队正在讨论处理一项风险的方法,他们确定了几项可选方案:工作外包;为团队成员提供更多的培训;持等待的态度,以确定风险是否会发生;对风险置之不理。在上述情况下,被遗漏的风险应对策略是______。
单选题Two months into a design project, the customer requested a modification
to the project. The change was made a without notify the project manager. During
the final testing phase, result were different from what was planned for, This
scenario is an example of which of following?
A. Poor definition of the test plan.
B. Poor development of quality management plan.
C. Poor use of scope change control.
D. Poor adherence to the communication plan.