单选题You are the project manager for a large government contract. The contract was signed a year ago for this three-year, multi-million dollar project. You were not involved in writing the contract or setting up change control procedures, but now you are being inundated with change requests from the project sponsor and from your own senior management. What should you do first?
单选题______is typically not referred to as a buffer type in critical chain project management.
单选题Using this data, what is the expected time for this activity? A) 12 days. B) 13 days. C) 17 days. D) 16 days.
单选题当合同明显不能正常完成时,一方放弃正当的权利应用什么术语表示?
单选题The difference between a project and a program is that the ______. A) program has many projects B) Project is typically longer than a program C) program is another name for process D) both B and C
单选题Of the four types of risk inherent in project management, which one
will have the most lasting effect from the customer's perspective if not managed
well?
A. Scope risk.
B. Schedule risk.
C. Cost risk.
D. Quality risk.
单选题下列关于项目生命周期、项目管理生命周期和产品生命周期的说法,正确的是______。
A.项目变化和发展时,项目生命周期通常随之变化和发展
B.项目管理生命周期对于每个项目都是独特的
C.项目管理生命周期就是项目生命周期
D.典型的产品生命周期包括多个项目生命周期
单选题 对于采购价值比较小,不值得花时间和成本进行过多比较的采购,可以采用哪种方法选择供应商?______
单选题在项目即将收尾的时候,卖方城市遭遇了百年罕见的高温,根据当地政府的要求,所有室外工作都被停止了,这导致了可交付成果的延迟。作为项目经理,你应该______。
单选题项目的成功离不开管理层的支持。下列哪一项能最恰当地描述管理层的角色?______
A.帮助项目团队编制项目计划
B.防止项目目标改变
C.确定项目约束条件
D.帮助项目团队把项目计划整合在一起
单选题What is true when a change control system's provision for changes without formal review in case of emergency is being utilized? A) Changes can be simply applied without further managerial activities if they help solving the problem. B) Changes must still be documented and captured so that they do not cause problems later in the project. C) A new change control board should be established. D) The project baseline must be changed as well.
单选题The project plan is used to do all of the following EXCEPT ______. A) document project planning assumption B) define the content of management reviews C) identify risks that arise during project execution D) provide a baseline for progress measurement and project control
单选题You are an expert in risk management,having worked in the field for more than 15 years.Your project is behind schedule and in your project.you are in the process of identifying which risks may affect your project through the risk identification process.In a discussion with your project sponsor,you mention that after the risk identification phase is completed,you would like to directly perform quantitative risk analysis.Your project sponsor cautions you against doing this-he mentions that in a prior project,qualitative risk analysis was conducted after risk identification.In this context,you will______. A) mention to your sponsor that since you are an expert in risk management, there is no need to do qualitative risk management and the team can directly go to quantitative risk management phase.This will also save time since your project is behind schedule B) agree with your sponsor that not doing qualitative risk analysis may mean some risks will remain unidentified and increase the probability of failure in your project C) mention to the sponsor that usually in your past experience,qualitative risk analysis was a waste of time and not recommended for this project D) mention to the sponsor that this is a type of project where qualitative risk analysis is not required.Specific categories of projects do not need qualitative risk analysis
单选题项目经理正在对项目的沟通工作进行定期检查,发现某位重要干系人未收到某项重要信息,项目经理要求向其补发。项目经理的工作属于以下哪个过程?______
A.规划沟通管理
B.控制沟通
C.管理沟通
D.识别干系人
单选题买方与卖方的一项工程施工合同已经执行了15个月时间。卖方已经向买方申请退还保留金。买方回复说,将在一周内退还50%的保留金。以下哪项最好地描述了该合同的情况?______
A.合同正处于执行阶段,买方对卖方的工作绩效不太满意
B.卖方提出了退还保留金的合同变更请求,买方部分同意
C.合同将在一周内关闭
D.卖方已经完成了合同的主体工作,合同处于收尾阶段
单选题 所有已经识别的风险都要经过下列所有过程,除了______。
单选题为纪念地质工作者对国家核工业发展所做出的重要贡献,你作为项目经理正在为政府建造一个永久性的开拓者纪念碑。在这种情况下,你认为临时性这种说法( )。 A.不适用于纪念碑建设工作,因为纪念碑要永久使用 B.不适用于要建造的项目产品 C.不适用于纪念碑建设团队 D.不适用于纪念碑建设团队,因为建设工作的持续时间较长
单选题下列哪项不属于制约因素的例子?______
A.客户事先确定的预算
B.强制性进度日期
C.项目过程中不发生不可抗力事件
D.合同条款
单选题在一个典型项目中,什么时候风险最高而影响最小?
单选题资源分解结构的主要作用是什么?______
A.有利于按时间段准备项目资源
B.有利于统一采购用于不同项目部位的同种资源
C.有利于指定每项工作的责任人
D.有利于考核团队绩效