单选题以下哪个最好地描述了开展项目变更控制的目的?( )A.确保所有变更都经过批准,确保只有经批准的变更才能纳入计划中B.确保所有变更都经过变更控制委员会的审批,并在批准后纳入计划中C.确保把项目变更控制在最少的范围内D.确保只有最重要的干系人才能提出变更请求,并参与对变更请求的审批工作
单选题 项目进行了一次精密仪器采购,这种设备只有唯一的一家供应商。由于项目未能按合同要求提供场地
单选题Which of the following statements is not true? A) Attribute sampling is the process of assessing whether results conform to specifications or not. B) Prevention means keeping errors out of the process by applying actions before the process starts changing its input. C) Variables sampling means that the result is classified into one of the 3 categories: "acceptable"-"acceptable after rework" "rejected" . D) Inspection is often mainly done to keep errors out of the hands of the customer instead of as a means of process control.
单选题Risk identification outputs include the following except______.
单选题Since your quality process was not up to the four sigma requirements desired by your customer, some of your products were rejected, and there is a potential that you would not get repeat business from the same customer. From a quality perspective. the costs associated with your products being rejected can also be categorized as ______ .A) cost of conformanceB) customer retention costsC) failure costsD) performance cost
单选题项目组织机构图可以展示以下所有,除了______。
单选题在以下哪种情况下,关键路径上的活动可能出现负的浮动时间?( )A.用顺推法所得到的完工日期晚于客户所要求的完工日期B.用逆推法所得到的完工日期晚于客户所要求的完工日期C.用顺推法所得到的完工日期早于客户所要求的完工日期D.用逆推法所得到的完工日期早于客户所要求的完工日期
单选题 项目已经结束,正在进行项目后评价,项目经理要求开展客户满意度调查。但有一名团队成员认为没有毖要
单选题在项目完成50%的时候,项目团队发现其中两个活动之间存在一种新的硬逻辑关系。项目团队首先应该______。
A.审查尚未开始的所有活动的进度安排
B.使用蒙特卡洛模拟技术,计算项目工期的可能分布情况
C.重新确定项目基准,确定对范围、进度和成本的影响
D.分析对新资源的需求,进行资源平衡
单选题In your project,you can use all the following tools and techniques for risk response planning EXCEPT______.
单选题The project scope statement furnishes a basis for ______.
A. future project decision including the criteria used to determine if the
project or phase has been successfully finished
B. provides link to the client functional management groups
C. allowing the project to move to the next phase
D. a way to provide updated information to the accounting
department
单选题All of the following are tools for scope verification EXCEPT ______. A) product review B) audit C) walk through D) sensitivity analysis
单选题 当地气象台刚刚发布了紧急暴风雨警报,预计2小时后有大暴风雨
单选题The decision to request an increase the resources for a project is the responsibility of the ______. A) functional manager B) project manager C) director of project management D) customer
单选题有争议的变更是在买卖双方不能就变更补偿达成一致的情况下而要求的变更。这种变更还可被称为以下各项,但不包括______。
单选题活动A历时为3天,开始于4号星期一早上,活动A有一个后续活动B。这两个活动之间是完成到开始关系,并有3天的时间滞后量。活动B历时为4天。按照项目日历,星期天为非工作日。从这些数据可以得到什么?( )A.两项活动的总持续时间为8天B.两项活动的总持续时间为10天C.活动B的结束日期为14号D.两项活动的总持续时间为12天
单选题一个项目经理和他的团队正在使用鱼骨图,努力确定将会有多少不同因素与某个潜在问题相关联。项目经理正参与质量管理的哪个过程?( )A.规划质量B.实施质量保证C.实施质量控制D.实施质量审计
单选题A planning package is a ______ .
单选题在项目执行期间,某个关键团队成员尚未完成相关工作,就被转派到另一个新启动的项目。这时,应该______。
A.要求延长工期
B.要求增加预算
C.提出变更请求
D.招聘新成员来从事剩余的工作
单选题下列关于资源平衡和资源平滑的说法,正确的是______。
A.资源平衡和资源平滑都不会导致关键路径的改变
B.资源平衡不会导致关键路径的改变,资源平滑则通常导致关键路径的改变
C.资源平衡只能在浮动时间允许的范围内进行,而资源平滑则允许延长完工日期
D.资源平衡往往导致关键路径的延长,而资源平滑则不会导致关键路径的延长