单选题清晰明确的目标对项目团队非常重要,这是因为它可以______。
单选题A team member notifies the project manager that the activities comprising a work package are no longer appropriate.It would be BEST for the project manager to be in what part of the project management process?
单选题Upon completing a project schedule, Roberta finds the critical path indicates the project will complete on April 15. As she works through the schedule, she finds there are several tasks with float. Task B has 10 days of free float, while Task F has 5 days of total float. If the start of Task B is delays, what is the completion date of the project?
单选题你在与外部项目利害关系者一起工作中将使用的主要的沟通技能是______。
单选题You are the project manager for software development project.The feasibility study can start any time and takes 1 week and requirement gathering takes 2 weeks which can start only after feasibility study.The design and test plan development can start in parallel after the requirements gathering.Test plan preparation takes 8 weeks followed by a review by the customer and the time estimated for review is 1 week.After the review,Test data preparation takes 6 weeks.Design takes 6 weeks and it is followed by development and unit testing,for one module it takes 2 weeks and for the other module it takes 2 weeks.There are no dependencies between modules and they can be developed simultaneously.After test data preparation and development and unit testing of both the modules,there is 2 weeks system testing.What is duration of the critical path?
单选题The following information is available about a particular task in your project plan:early start(ES), 25 days;late start(LS), 30 days;early finish(EF), 50 days;late finish(LF), 55 days. Based on this information。you can deduce that______. A) the project float is 5 days B) the project may get delayed C) the task is not on the critical path D) the task is on the critical path
单选题小李被上级领导安排管理一个项目。虽然项目本身并不大,但小李感觉工作起来非常吃力,因为除了把必要的信息传递给不同团队成员及他们所在部门外,他甚至不知道下一步的工作安排。他处在______组织结构中。
单选题以下哪个是定量风险分析的工具与技术?______
单选题机械设备安装项目中,需要大量采购某种标准化产品。这一类产品的生产工艺成熟,市场上有很多厂家可以供货。要采购这种产品,最佳的方式是什么?( )A.英特网搜索B.发布采购广告C.招标采购D.向特定卖方发定单
单选题下列哪项不是项目人力资源管理计划的组成部分?______
A.工作岗位及其权责
B.资源直方图
C.组织结构图
D.人员配备管理计划
单选题以下关于采购工作说明书的说法都是正确的,除了______。
单选题Which of the following is not used in the quality control process? A) Gantt charts. B) Control charts. C) Pareto charts. D) Statistical sampling.
单选题项目实施中,项目业主通常有权在项目工作结束前指令进行工作范围变更。如果业主在项目将要结束时突然口头要求承包商进行某一范围变更,且坚持不发布书面变更令。这种情况下( )。A.实施该变更的成本将全部由业主承担B.业主应在变更实施之前支付一半的成本,在变更完成之后再支付另一半C.承包商将承担与该变更有关的全部风险D.如果变更不大,承包商应该实施该变更
单选题在给项目建议书评分的时候,可以采用多种技术,但所有的评分技术都将利用______。
单选题你的朋友刚刚被任命为一个供电项目的项目经理,不过他的工作进行得似乎并不顺利,大量的要求、命令由他发布,可执行的结果却往往和要求大相径庭。为了能让干系人更准确地理解项目经理传递的信息,你建议他应该更关注______。
单选题 为了检查代码的质量,项目经理要求每位团队中的专家编完代码后,交给其他专家做平行审查,以便识别问题
单选题在你公司内,你在决定是否购买某产品或者自己生产。下列所有关于购买一自制分析的说法都是正确的,除了:
单选题为了解决A小区的停车困难,开发商启动了一个扩建停车场项目。为了减少该项目建设给居民生活带来的不良影响,并保证项目顺利进行,高级管理层要求你提交风险管理计划,并识别风险。你将邀请谁参与风险识别工作?______
A.项目管理团队的成员
B.风险管理的专家
C.周边居民
D.全部项目干系人
单选题使用凸显模型对干系人进行分析,应该考虑以下所有,除了______。
单选题对要实施的服务或项目中的物理项、过程或服务的详细描述被称为______。
