单选题 某团队成员组织各供应商召开协调会来解决问题。项目经理发现参会人数很多,有管理层、技术员
单选题Effective stakeholder management includes all of the following project elements EXCEPT ______ .
单选题定义活动过程是对以下哪项进行定义和规划?( ) A.进度活动 B.工作包 C.汇总活动 D.里程碑
单选题Company ABC adopt year-summary for decritiation of asset.They spent $17000 purchased one computer.It is eatimated that the computer can be sold with $2000 three years later。Thus,how much will be the asset decritiation of this computer in year three?
单选题A projeet team budgeted US $3,000 for the work performed and has spent US $4,000 to date. If they budgeted US $5, 000 for the work scheduled, what is the cost variance?A) $-1,000.B) $2,000.C) $1,000.D) $-2,000.
单选题可以使用下列各种方法计算挣值,除了( )。A.顺推计算法B.加权里程碑法C.固定公式法D.完成百分比法
单选题Company procedures require the creation of a lessons learned document.Which of the following is the BEST use of lessons learned?
单选题What is the meaning of upper control limit and lower control limit in control charts?
单选题What is the meaning of upper control limit and lower control limit in control charts?A) Specification limits.B) Acceptable range of the variance of a process.C) Acceptable range of the variance of a product.D) Customer requirements.
单选题为了加快项目进度,你决定在全部文件编写工作结束之前3天就开始文件印刷的版面设计工作。这是一种什么逻辑关系?______
A.带时间滞后量的开始到开始关系
B.带时间提前量的完成到开始关系
C.带时间提前量的开始到开始关系
D.带时间滞后量的完成到开始关系
单选题如何在结束采购过程中进行经验教训总结?______
A.开展采购审计
B.开展采购绩效审查
C.开展检查与审计
D.使用记录管理系统
单选题在审查项目的工作绩效信息时,你发现项目中的某项工作的成本偏差百分比为7%。项目的成本管理计划中所规定的控制临界值为±10%。你应该______。
A.立刻调查根本原因并采取纠正措施 B.继续监视事态发展
C.获得更有经验的人员来开展项目工作D.向发起人要求增加资金
单选题项目经理正同承包商谈一个总价加激励费用合同。合同的目标成本是200000美元,目标利润是30000美元,这个合同规定了最高价是270000美元,共享比例是70/30。如果承包商完成合同时实际成本是170000美元,买方要付给承包商的利润是______。
单选题在招标阶段,项目小组的任务是______。
单选题You are assigned as the project manager to a project which is executed for a customer under FP contract.Your customer informed you this morning that they insist on certain“refinements”of the project scope.You agree that the requested actions make really sense to the project,but believe that they constitute a major change increasing the project scope.What should you do next?
单选题Milestones established by the customer must be adhered to by ______ A) project manger B) functional managers C) the customer D) both A and B
单选题可以用散点图表示两个变量之间的相关性。两个变量之间的关系的密切程度,取决于数据点分布( )。A.靠近某条横直线的程度B.靠近某条竖直线的程度C.靠近某条曲线的程度D.靠近对角线的程度
单选题Since your quality process was not up to the four sigma requirements desired by your customer, some of your products were rejected, and there is a potential that you would not get repeat business from the same customer. From a quality perspective. the costs associated with your products being rejected can also be categorized as ______ .
单选题项目经理经常使用哪种沟通方法来发布项目绩效报告?______
A.交互式沟通
B.非正式沟通
C.推式沟通
D.拉式沟通
单选题In your project, you realize the importance of determining the start and finish dates for project activities. If the project start or end dates are not realistic, then the project may not be completed on time. This is done as part of ______ . A) activity sequencing B) activity duration estimating C) schedule development D) activity definition