单选题Cost control outputs include all of the following EXCEPT ______ .A) estimate at completionB) budget updatesC) revised cost estimatesD) cost baseline
单选题 公司经过商业论证后准备上马一个新项目。一旦项目正式立项,你将是该项目的项目经理
单选题以下哪项通常不包括在工作绩效信息中?( )A.可交付成果的完成情况B.项目进展情况C.项目的累计成本支出情况D.项目的累计成本偏差情况
单选题A metric is an operational definition that describes, in very specific terms, what something is and how the quality control process measures it. A measurement is an actual value. For example, it is not enough to say that meeting the planned schedule dates is a measure of management quality. The project management team must also indicate whether every activity must start on time or only finish on time and whether individual activities will be measured or only certain deliverables and if so, which ones. Some examples of quality metrics include defect density, failure rate, availability, reliability and test coverage. In this context, quality metrics should be used during ______ (select the best answer).A) quality assuranceB) quality planningC) quality controlD) quality assurance, quality control
单选题In order to speed up a project, you made a decision to fast-track a phase currently performed with five team members and another one which was planned to begin in four weeks time with another five team members. Which of the following activities should you do first? A) Make sure that all exit criteria of the consecutive phase have been met to ensure the flow of communications in a team situation which is more complex by a factor of 2. B) Make sure that all entry criteria of the previous phase have been met by planning and performing a phase gate meeting to assess technical aptness. C) Make sure that all exit criteria of the previous phase have been met by planning and performing a phase gate meeting to assess technical performance. D) Restructure your team and delegate tasks in order to ensure the flow of conmunications in a team situation which is more complex by a factor of 4.5.
单选题Which type of project cost estimate is the most accurate? A) Preliminary. B) Definitive. C) Order of magnitude. D) Conceptual.
单选题对软件开发企业来讲,项目成功有两个明显的标志,一是合同款全额收回,这标志着企业本身的项目目标已达到,二是软件用户在使用过程中没有软件功能或质量方面的投诉,这标志着用户的项目目标也达到了。要达到这两个目标可不是件容易的事情,需要广泛汲取以前类似项目的经验教训,使用以前积累的组织过程资产。谁负责积累项目管理方面的组织过程资产?( )A.项目经理B.项目集经理C.项目组合经理D.项目管理办公室
单选题You are the project manager managing the setting up of an oil rig in the Pacific Ocean. Which of the following could be a valid constraint when you are doing human resource planning for your project?
单选题Which one of the following estimates should least reflect the actual
cost of the project ?
A. Order of magnitude.
B. Approximate.
C. Definitive.
D. Detailed design.
单选题与分包商签订了成本加激励费用合同,合同估计成本20000元,奖励费用2000元,买卖双方风险分担比率30:70。如果实际成本为22000元,买方应支付的总价为______。
单选题哪个理论认为,个人在不同程度上有成就需要、权力需要与亲和需要三种需要,管理者应该根据个人更重视的需要来制定激励措施?______
A.麦克利兰的成就动机理论
B.弗鲁姆的期望理论
C.赫兹伯格的双因素理论
D.麦格雷戈的X/Y理论
单选题组织过程资产可以分为哪两大类?( )A.流程与程序、共享知识库B.标准与规范、项目管理信息系统C.模板与指南、基础设施D.控制程序、工作授权系统
单选题你决定找到优势互补的另一个合作伙伴,组成联合体参与项目工作,这种积极应对风险的策略是______。
单选题在规划干系人管理过程中需要用到专家判断这个工具技术,是为了______。
单选题在风险管理中,风险责任人的主要责任是______。
单选题工作绩效测量结果中通常包括( )。A.可交付成果的状态B.进度绩效偏差C.进度进展情况D.预测数据
单选题在项目实施过程中,应该使用以下哪个工具来了解风险的发展趋势、识别新风险、删去已过时的风险?______
A.技术绩效测量
B.偏差和趋势分析
C.风险审计
D.风险再评估
单选题A work authorization system can be used to______. A) manage who does each activity B) manage what time and in what sequence work is done C) manage when each activity is done D) manage who does each activity and when it is done
单选题项目进入收尾阶段,买方(客户)要求对范围做重大变更,项目经理应当怎么做?______
A.通知管理层
B.如果变更有利于提高项目效益,则接受变更
C.告诉客户,这个时候不能再做此变更,建议客户就此签订新合同
D.向变更控制委员会提交变更申请
单选题在实施定量风险分析的工具与技术中,以下哪种是数据收集和展示技术?______
A.访谈
B.敏感性分析
C.预期货币价值分析
D.蒙特卡洛模拟