单选题项目需求包括下列所有,除了( )。A.产品性能需求B.商业需求C.项目管理需求D.交付需求
单选题项目已经进入收尾阶段,应该由______向卖方发出可交付成果已经通过验收或未通过验收的正式书面通知。
单选题 项目经理给虚拟团队的专家发送了工作邮件,该专家一直未回复,项目团队本周内就要提交整合的报告
单选题There are specific absolutes for a comprehensive quality program.
These are ______.
A. conformance to WBS
B. fitness of use and involvement during the planning phase
C. fitness of use and fitness for purpose
D. none of the above
单选题项目拟用的挣值管理规则应该在以下哪个文件中作出规定?( )A.项目成本管理计划B.项目进度管理计划C.项目范围管理计划D.项目变更管理计划
单选题以下都是采购管理计划的内容,除了______。
A.拟采用的合同类型
B.与采购有关的风险管理事项
C.如何管理多个供应商
D.采购工作说明书
单选题 风险再评估与风险审计都是监控风险过程的工具,它们之间的主要差别在于______。
单选题下列哪项权力可以对下级和上级都能产生实质性的影响?( ) A.正式权力和专家权力 B.奖惩权力和正式权力 C.专家权力和参照性权力 D.专家权力和惩罚权力
单选题All of the following are true quality statements except:A) Quality improvement depends upon better definition and increased awareness of the requirements/specifications.B) Project quality management must address both management of the project and the product of the project.C) Recognition of key actions required of each team member is necessary to meet quality objectives.D) Computer aided design systems can improve quality, but only at the expense of an increase in the cost of design.
单选题The project team has added some additional functionality which was not required as part of the project. However the customer is satisfied with the project. From a quality perspective, ______ .
单选题你刚刚组建了项目管理团队,其中包括3个全职工作人员和4个兼职工作人员。所有人员都来自公司内部,本来就相互认识,而且大多数都曾经在一起合作过。你首先应该( )。A.与每一个成员单独见面,讨论角色与职责B.编制责任分配矩阵,并分发给每个成员C.组织成员编制工作分解结构D.召开启动会议
单选题项目执行到一半时,你被推选为新任的项目经理。在就职会上,你向团队成员阐述了项目的愿景,并鼓励所有团队成员为了这个共同的愿景而努力。这是哪种人际关系技能的展现?______
A.领导力
B.影响力
C.激励
D.沟通
单选题Calculate the standard deviation of a task if O=4,P=10,M=6.
单选题项目经理通过______来反映项目沟通的复杂程度。
单选题以下哪项最好地描述了异常情况报告?______
A.异常情况报告是定期编制的
B.异常情况报告是为防止出现异常情况而编制的
C.异常情况报告是关于超出控制临界值的不利情况的报告
D.异常情况报告是供项目团队成员使用的绩效报告
单选题Cost performance measurement is BEST done through which of the following? A) Asking for a percent complete from each team member and reporting that in the monthly progress report. B) Calculating earned value and using the indexes and other calculations to report past performance and forecast future performance. C) Using the 50/50 rule and making sure the life cycle cost is less than the project cost. D) Focusing on the amount expended last month and what will be expended the following month.
单选题在合同履行的过程中,项目团队成员对使用哪种地板砖有不同意见。材料的质量和价格因品牌的不同而不同。作为项目经理,你将建议他们查阅下列哪个项目文件来解决他们的争议?( )A.采购文件B.采购工作说明书C.项目计划D.项目合同
单选题Activity duration estimate inputs include all of the following EXCEPT ______ .
单选题Sally, the project manager, was working with two of her team members to resolve a conflict. Although one party, Bill, had withdrawn, and the other, Kathleen, was attempting to compromise, the resolution was slow in coming. Due to the negative impact a non-resolution would have on a critical milestone which was quickly approaching, Sally brought the two together to confront the issue. Neither would work with Sally to resolve the issue. Sally finally listened to both sides and made a decision, which favored Bill's position more than Kathleen's position. What forms of conflicts resolution did Sally finally use to resolve the problem?
单选题以下哪个是风险转移的例子?______
A.从项目中取消一项风险高的工作
B.选用比较稳定的供应商
C.要求供应商提供履约担保
D.建立应急储备