单选题An activity has an optimistic estimate of 10 days, pessimistic estimate of 16 days, most likely estimate of 13 days. Assuming a normal distribution, what is the probability that the task will be completed within 10~16 days?
单选题项目经理不断地向团队成员强调,必须在整个项目期间与干系人进行沟通和协作,引导干系人对项目的期望,解决与干系人之间实际出现的问题,提升干系人对项目的支持程度。他所强调的工作属于以下哪个过程?______
A.识别干系人
B.规划干系人管理
C.管理干系人参与
D.控制干系人参与
单选题You are in the development phase of a software project and meeting the development team to collect the status.You want to show the team members the actual dependencies of different tasks.Which scheduling tool you will be using to explain them(choose the best answer)?
单选题在项目阶段结束时,要对该阶段的可交付成果和绩效进行审查,其目的在于( )。A.做出项目变更(包括纠偏)、项目继续或不继续的决策B.获得客户对可交付成果的认可C.调整项目目标D.根据资源情况来决定是否需要补充资源
单选题项目进度压缩方法与以下哪个方法最为相似?______
A.范围蔓延
B.范围优化
C.价值工程
D.价值分析
单选题Including a contingency reserve in the project budget is intended to ______ .A) reduce the probability of scope changesB) increase the probability of scope changesC) reduce the probability of a cost overrunD) increase the probability of a cost overrun
单选题在监控项目时,预测项目将不能在规定的日期完工。项目无法获得额外的资源。本项目是低风险的,效益成本比预计是2.0,活动之间依赖关系主要是根据团队的偏好确定的。这些情况下,最好应该______。
A.把资源从选择性依赖关系调往外部依赖关系
B.削减活动的资源
C.使更多活动同时进行
D.从项目中取消一项工作
单选题 在项目执行阶段的高峰期,某个关键活动的几名重要技术人员突然一起提出要离开项目
单选题What does cost of quality mean?A) The sacrifice of unessential project objectives to meet essential quality standards.B) The life cycle cost of the proj ect.C) Determining the costs incurred to ensure quality.D) The cost of meeting project objectives.
单选题某项目是高风险项目,风险管理特别重要。在分析项目风险时,项目管理团队需要开展风险数据质量评估,以便______。
单选题以下都是合同提前终止的原因,除了______。
单选题教育、培训和保险是______的例子。
单选题以下哪个属于运营的一部分?( )A.会计业务B.调整现有运营系统C.产品更新换代D.服务流程再造
单选题 风险管理计划中通常包括下列哪项?______
单选题If Task C has 0 days of free float and 0 days of total float, what does this mean to the project? A) The project does not have adequate lead and lag times built in. B) The task is on the critical path. C) The duration of the task should be compressed. D) The dates for the task are not accurate.
单选题Resource calendars affect a specific resource or category of resources. They reflect how some resources work only during normal business hours, while others work three full shifts, or a project team member might be unavailable, such as on vacation or in a training program, or a labor contract can limit certain workers to certain days of the week. Resource calendars are valuable inputs for ______ .
单选题在管理干系人过程中,项目经理通过对重要干系人施加影响,使他们支持项目,这是在使用以下哪个工具与技术?______
A.沟通方法
B.沟通技术
C.管理技能
D.分析技术
单选题以下所有都是制订进度计划过程的输出,除了______。
A.项目进度模型
B.进度管理计划
C.进度数据
D.进度基准
单选题验收的可交付成果是下列哪个过程的输出?( )A.收尾过程B.监控过程C.执行过程D.规划过程
单选题下列哪种组织结构中,项目最不受到关注?______
A.平衡式矩阵
B.紧密式矩阵
C.职能型
D.项目型