单选题A recommended corrective action is an output of which cost management process area? A) Resource planning. B) Cost estimating. C) Cost budgeting. D) Cost control.
单选题 你刚刚在启动大会上被任命为项目经理
单选题项目管理团队正在讨论风险应对规划。他们讨论了如下几种可能的应对措施,包括工作外包、购买保险、置之不理、把工作分配给更有经验的人、在项目进行过程中增加测试次数、增加应急储备、对员工进行更好的培训。他们没有涉及的应对措施是______。
A.风险转移
B.风险缓解
C.风险规避
D.风险接受
单选题Although your internet start-up company has few project management policies and procedures in place, it made a healthy profit last year. Experience, however, has taught you that some controls are required, especially for projects that change frequently. You would like to establish a change control system for your company, but must convince a group of money-hungry “20 somethings” to use it. To be effective, the change control system must include ______.
单选题A thorough review of______will help identify potential risks to the project.
单选题You have been having a lot of heated discussions with your colleague about an issue. and this is resulting in a hostile environment. To “cool-off” this hostile situation, you agree to your colleague's point of view. The conflict resolution mode that you are using is ______ .
单选题The first phase of a project is the feasibility study. According to the PMBOK, which of the project management process group does the feasibility study phase need?
单选题Which information is NOT found in the project charter?
单选题你正在南方一个沿海小城管理着一个高精密、技术复杂的、防入侵的数据中心建设项目。此数据中心承担着国内多家大型制造企业的多年运营数据。尽管这一地区具备强大的经济优势,但台风的威胁还是使你制定了一项备用计划,以确保该数据中心遭洪水时备份系统能在1000公里以外安全运行。这是______类型的风险应对。
单选题核对表分析是以下哪个过程的工具与技术?______
单选题作为项目评估和竞价阶段的一部分,项目所有者(买方)必须考虑团队人员的合作性和人事变更。如果项目的所有者(买方)提出替换可能不称职的员工,你作为承包商,针对这种要求,你的义务是什么?
单选题下列哪个文件把产品需求与需求源及满足该需求的可交付成果连接起来?______
A.范围管理计划
B.需求管理计划
C.需求文件
D.需求跟踪矩阵
单选题Checklists are completed in which process?
单选题在时间非常紧张的情况下做决策,应该使用以下哪种决策方式?______
A.命令或随机
B.命令或咨询
C.咨询或协商
D.协商或随机
单选题The five project management process groups are ______ . A) planning, checking, directing, monitoring, and recording B) initiating, planning, executing, monitoring and controlling, and closing C) planning, executing, directing, closing, and delivering D) initiating, executing, monitoring, evaluating, and closing
单选题工作绩效信息是以下所有过程的输入,除了( )。A.实施质量控制B.控制范围C.控制进度D.控制成本
单选题Negotiation across international cultures involves mutual interdependence between parties. The negotiation MUST be conducted in an atmosphere of ______ .
单选题I Which project management process group is managing stakeholders in?
单选题在某建设工程项目的地基开挖过程中,对于因气候原因造成的进度拖后风险,项目经理采取了风险接受的策略。由于在施工期间下特大雨,工程不得不停工3天。项目经理应该( )。A.使用应急储备B.把项目工期延长3天C.要求保险公司赔偿D.与团队成员开会讨论处理方案
单选题在采用固定价格合同时,买方决定增加项目范围以获得更好的产品。在这种情况下,买方可以做下列所有事宜,除了______。