单选题你负责的一个项目比预期完工时间晚了1周,为了保证在接下来的几个月都有可以持续数量的资源使用,你必须重新安排资源,这属于______。
单选题 一份好的招标文件,必须具备以下特点,除了______。
单选题Which of the following type of contracts is most preferable to the
contractor doing the project work?
A. Cost plus fixed fee.
B. Fixed price.
C. Fixed price and incentive fee.
D. B and C.
单选题在制订进度计划时,如何设法克服资源制约因素的不利影响?( )A.赶工B.使用蒙特卡罗方法C.采用快速跟进方法D.进行资源平衡
单选题权变措施是在风险管理的哪个阶段确定的?
单选题项目经理发现一个团队成员的工作表现不佳。他处理这个问题的最好沟通方法是______。
单选题To crash a schedule you should ______. A) increase the time allowed on those tasks that have float B) try to increase expenditures of time on only those tasks that are behind schedule C) replace those workers that are not performing up to par with the busy workers D) increase work efforts on those tasks that are on the critical path
单选题You have taken information on project scope and resources and then developed durations for input to schedules. Since there was very limited information about the project, you used actual duration of a previous, similar activity as the basis for estimating future activity. What will be a next step after this activity?
单选题An example of scope verification is ______ .
单选题人际关系技能是以下哪个过程的工具与技术?______
单选题What is done after a feasibility study?
单选题The project manager has just received a change from the customer that does not affect the project schedule and is easy to complete. What should the project manager do FIRST? A) Make the change happen as soon as possible. B) Contact the project sponsor for permission. C) Go to the change control board. D) Evaluate the other components of the "triple constraint" .
单选题在项目整合管理中要使用哪个工具与技术来实施各过程?( )A.项目管理方法论B.专家判断C.挣值技术D.项目管理信息系统
单选题You are the project manager responsible for developing a software application based on customer requirements.As the customer requirements keep changing frequently,what tool can you use to conduct integrated change control of your project? A) Project selection methods. B) Additional planning. C) Corrective action. D) Project management information system.
单选题In risk response planning,you are in the process of developing options,and determining actions to reduce threats to your project's objectives.When you show the results of your risk response planning to your project sponsor,she is not comfortable with the risks in the project and she suggests that the project scope should be decreased.This is an example of______.
单选题 某个新产品研发项目
单选题启动过程组旨在( )。A.正式授权开始一个新项目或现有项目的一个新阶段B.批准市场分析报告以保证采取正确的市场行动C.采用合适的项目选择过程D.批准项目可行性研究报告
单选题在规划采购管理过程中,经常需要从外部寻求以下各种专家的专家判断:______。
单选题你们正处于编制采购文件的过程中。如果打算以价格为基础来选择卖方,那么采购文件可以使用下列名称,除了______。
单选题项目准备收尾时,团队成员识别出一个新风险,作为项目经理,你应该______。
A.通知项目干系人
B.实施风险减轻策略
C.实施定性风险分析
D.制订权变计划