单选题在管理干系人参与过程中,一些老问题被解决,新问题又出现。应该最先动态更新以下哪个文件?______
单选题One of the fundamental tenets of modern quality management is:
单选题采购谈判是以下哪个过程的工具与技术?______
单选题以下哪个是外部风险的例子?
单选题In what way does free float differ from total float? A) Free float is the amount of total float that does not affect the end date, whereas total float is the accumulated amount of free float. B) There is no difference-the two terms are functionally equivalent. C) Free float is the amount of time that a schedule activity can be delayed without delaying the early start of any immediately following schedule activities, whereas total float is concerned with delays that do not affect the project finish date. D) An activity's free float is calculated by subtracting its total float from the critical path's total float.
单选题Output from the activity resource estimating process includes ______ .
单选题Rebaselining may be required in cost control when ______ .
单选题以下关于项目生命周期的说法,正确的是( )。A.通常相互交叉而有时又按顺序排列的各阶段的集合B.指启动、规划、执行、监控和收尾等五个过程组的集合C.不同的组织通常采用阶段名称相同、阶段数量相同的项目生命周期D.通常按顺序排列但也可能相互交叉的各阶段的集合
单选题项目发起人是项目最重要的干系人之一,他的需求满足程度将对项目产生很大的影响,作为项目经理,你应该高度重视与发起人的沟通。目前处于项目启动阶段,如果发起人问你:“现在预计全部工作的成本是多少?”由于你使用挣值管理技术,你应当计算______。
单选题以下哪项是组建项目团队过程的输入?______
A.活动资源需求
B.资源日历
C.组织结构图
D.人力资源管理计划
单选题你所管理的项目将需要在多个物理地点展开,涉及的风险比较多。你从公司的组织过程资产中了解到,过去类似项目的风险管理工作比较混乱。你想要在本项目上改变这种局面。为了有效地管理本项目的风险,你首先应该______。
A.识别潜在的风险及影响
B.指定专门人员负责风险管理
C.编制风险管理计划
D.编制风险登记册
单选题Project team A has been hired to manage a transportation project very similar to dozens at projects they've managed successfully in the past.The team had determined that the probability of achieving project objectives is 94%.The team has determined the size of contingency reserves that may be needed.These determinations are included in which process?
单选题在结束采购中采用______工具与技术。
单选题Which of the following is true about critical chain?
单选题下列哪项是正确的?( )A.经过批准的项目计划,并非就要保持不变,而是通常要渐进明细、不断更新B.如果项目产品需要后续支持和维护,那么项目就可以长期延续下去C.项目不是独特的,因为总会在某些方面与以前的项目类似D.由于软件开发完成后,还要进行软件的日常维护,所以软件开发项目不具有临时性
单选题指导与管理项目工作过程的工具是______。
A.项目管理计划
B.变更控制会
C.项目管理信息系统
D.项目管理计划更新
单选题以下哪个关于关键链的说法是正确的?______
A.关键链是关键路径的另一个名称
B.关键链是次关键路径的另一个名称
C.关键链表示的是一系列活动之间的硬逻辑关系
D.关键链是资源约束下的关键路径
单选题Which of the following is not used in the quality control process?
单选题Cost of quality is the total cost of all efforts to achieve product/service quality,and includes all work to ensure conformance to requirements.All of the following are costs that are incurred EXCEPT______.
单选题确定项目相关的质量计划并确定项目如何满足标准是______过程。
