单选题以下都是质量保证的目的,除了______。
A.提高项目干系人对项目将要达到质量要求的信心
B.进行过程持续改进,减少非增值活动
C.消除导致质量不合格的原因
D.重新评价质量标准,确保质量标准的可行性
单选题The project team is working on an important and complex project that requires a lot of coordination.Under these circumstances,the BEST strategy is to______. A) have a war room B) hire a contractor C) hold more meetings to get the word out D) gain extra assistance from management
单选题不遵守下列哪种逻辑关系,会给项目带来最大的不利影响?( )A.外部逻辑关系B.选择性逻辑关系C.软逻辑关系D.硬逻辑关系
单选题At the end of the closing process group, ______. A) it is verified that the defined processes are completed within all the process groups to close the project phase B) it is determined that the product of the project is completed satisfactorily C) project management plan is written off by the project sponsor D) new change requests are initiated as required
单选题可以为应对风险制定弹回计划,以便______。
单选题通常在项目的哪个阶段运用类比估算方法来估算项目持续时间或成本?______
A.启动
B.规划
C.执行
D.监控
单选题用以对付已发生风险的权变措施应被记录并纳入______过程中。
单选题以下关于固定总价合同的说法,正确的是______。
单选题During the completion of work packages,the sponsor asks the project manager to report on how the project is going.In order to prepare the report,the project manager asks all the team members what percent complete their work is.There is one team member who has been hard to manage from the beginning.In response to being asked what percent complete he is,the team member asks,“Percent complete of what?”Being tired of such comments,the project manager reports to the team member's boss that the team member is not cooperating.Which of the following is likely to be the real problem?
单选题Company ABC adopt year-summary for decritiation of asset.They spent $17000 purchased one computer.It is eatimated that the computer can be sold with $2000 three years later。Thus,how much will be the asset decritiation of this computer in year three? A) $5000. B) $4500. C) $7500. D) $2500.
单选题A thorough review of______will help identify potential risks to the project. A) risk identification checklists based on historical information and knowledge B) the project's change control system C) the project's mission statement D) the project's budget
单选题项目上发生了一个事件,对项目的进度和成本产生了不利影响。以前,项目团队曾识别出项目可能发生这个事件,但没有预计到后果这么严重。为了减轻该事件对项目进度和成本的不利影响,项目经理应该______。
A.查看风险登记册,执行应急计划
B.动用管理储备,来采取更好的应急措施
C.取消会受该风险影响的项目工作
D.进行风险分析,提出变更请求,采取权变措施
单选题Setting the number of defects is a direct responsibility of ______.
A. a functional worker
B. the project manager
C. management
D. the accounting department
单选题A particular stakeholder has a reputation for making many changes on projects. What is the BEST approach a project manager can take at the beginning of the project to manage this situation? A) Say "no" to the stakeholder a few times to dissuade him from submitting more changes. B) Get the stakeholder involved in the project as early as possible. C) Talk to the stakeholder's boss to find ways to direct the stakeholder's activities to another project. D) Ask that the stakeholder not be included in the stakeholder listing.
单选题通常而言,标书和建议的区别在于:
单选题You have just discovered an error in the implementation plan that will prevent you from meeting milestone date. The BEST thing you can do is to ______ .
单选题An example of scope verification is ______ .A) review the performance of an installed software moduleB) managing changes to the project scheduleC) decomposing the WBS to a work package levelD) performing a benefit/cost analysis to determine if we should proceed with the project
单选题可供查询的概率和影响矩阵,一般是由谁来设定的?______
单选题你在一个长期项目中工作,该项目对其顾客和用户有若干益处。因此,你作为项目经理,最先要做的事情之一就是识别对于项目成功至关重要的干系人。由于该项目在完工后将需要组织予以长期支持,因此关键干系人是______。
单选题在整个项目过程中,获得客户对已完项目范围及其相应可交付成果的正式验收,属于下列哪个过程?______
A.结束项目或阶段
B.结束采购
C.控制质量
D.确认范围