单选题估算活动资源过程的输出包括( )。A.资源价格B.活动持续时间估算C.资源分解结构D.出版的估算数据
单选题The statistical method that looks at the influence of different factors
on specific variables is called ______.
A. design of experiments
B. benchmarking
C. variability of factors
D. ISO
单选题The project charter is created by ______. A) the project manager B) upper management C) the vice president over a functional management group D) the customer
单选题 随着项目的不断实施,项目团队应该经常分析积极或消极风险对项目计划的影响,以便______。
单选题Organizations perform work to achieve a set of objectives. All of the following are true about projects and operations work EXCEPT:
单选题人员的预分派不适用于______。
单选题A project manager has to resolve two problems. However, both problems can occur in a single trial. In this situation, what is the BEST action the project manager can take?
单选题Activities that are related and shown as a single, aggregate activity reported at a summary level are called ______ . A) master schedule B) hammock C) WBS D) hanger
单选题Who is responsible for completing the lessons learned documentation? A) Project team. B) Sponsor. C) Project architect. D) Project manager.
单选题工作绩效报告产生于哪个过程组?______
A.规划过程组
B.执行过程组
C.监控过程组
D.收尾过程组
单选题 以下哪个属于风险起因?______
单选题范围基准包括以下组成部分,但不包括______。
单选题结束项目或阶段的依据包括以下所有,除了( )。A.项目管理计划B.验收的可交付成果C.事业环境因素D.组织过程资产
单选题项目工作绩效报告中包括如下数字:PV=110,EV=100,AC=120,总预算为150。成本偏差是多少?______
A.-20
B.-10
C.+10
D.+20
单选题某人已经被委派为项目经理,负责某条生产线的设计与建设项目。今天,他接到了一个重要干系人的询问。公司生产部门经理想了解在项目建设阶段将进行几次移交前的试运行测试。为了给出准确的答复,项目经理应该查看在以下哪个过程中开发的文件?( )A.估算活动持续时间B.核实范围C.定义范围D.制订进度计划
单选题在收集需求过程中,需要逐一、深入地了解每一个干系人的具体需求。最好使用下列哪个技术?______
A.访谈
B.问卷调查
C.焦点小组
D.引导式研讨会
单选题 对方说“我已经订好了明天晚上8点的飞机,我们必须在明天下午5点前达成一致”
单选题以下都是规划采购管理过程的输入,除了______。
单选题PERT provides project managers with the following ______. A) a basis for obtaining the necessary facts for decision making B) the basic structure for the reporting of information C) a graphical depiction of task internal-dependencies D) A, B and C
单选题 某项目受各种因素的影响已停工半年,由于市场环境变化,该项目已不再具备商业价值