单选题交付项目时,客户提出可交付成果与他们的需求不符,他们需要在可交付成果中增加额外产品,项目经理首先应该______。
单选题针对一个项目,假定的风险分析最好是通过一个结构化的方法论来完成,以便使得所有项目的因素都被评估。用于项目风险的结构化分析的最合适的工具是______。
单选题买方与卖方签订了一个成本加激励费用合同。合同规定的目标成本为320,000元,目标激励费用为45,000元,成本分摊比例为80/20,最高激励费用为62,000元,最低激励费用为11,000元。如果卖方实际成本为380,000元,则买方应支付的激励费用为( )。A.45,000元B.42,500元C.36,500元D.33,000元
单选题项目管理办公室( )。A.其经理通常直接向组织的CEO汇报工作B.开发项目管理的政策、程序和模板C.调配与管理各项目所需的全部资源D.协调管理一系列相互关联的项目
单选题A customer is not happy with a project deliverable. What is your BEST course of action?A) Tell the customer it meets the scope of work and get the customer's agreement to proceed.B) Determine why the customer is unhappy with the deliverable.C) Meet with the team to determine changes needed.D) Meet with the customer and offer a substitute project deliverable.
单选题In a project status meeting, you identified that a team member has not completed the task which he was supposed to complete this week. What action you will take as a project manager in a metrics organization? A) Update the details in work product information and share that with functional manager. B) Update the details in performance measurement baseline and share that with functional manager. C) Have an informal discussion with the team member to find out the reason. D) Formally communicate the slippage from the team member to the functional manager and request him to discuss with the employee to ensure that this will not happen in the future.
单选题 工作绩效信息中不包括______。
单选题项目经理在管理项目时,应该能够以合理的行动来把项目管理知识应用于实践。以下哪项对项目经理如何行动有最重要的作用?( ) A.项目经理的项目管理知识 B.项目经理的项目管理实践能力 C.项目经理的个人素质 D.项目经理的整合能力
单选题项目中的三个活动关系如下:任务B可以在任务A结束后开始,任务C可以在任务B开始后的第三天开始,任务B和任务C之间属于______关系。
单选题把项目计划编制成文档并且分发的主要目的是( )。A.在项目执行进程中减少不确定性B.促进项目干系人之间的沟通C.进行成本控制D.评估其他的项目备选方案
单选题The critical path ______. A) is the earliest series of events and activities which have the highest technical risk in the project B) is the series of events and activities which have the highest cost in the project C) is the longest chain of events and activities from today's date to the end of the project, if the plan represented by the current network plan is executed D) is an interesting concept, but is has little significance to the project functional managers assigned to the project
单选题一项工作,平均工期是10天,标准差是1.1天,在11.1天内完成的概率是______。
单选题The method of analyzing the sequence of activities with the least amount of scheduling flexibility to control the schedule is called______.
单选题The project manager can enhance project communications and team building by doing all the following except______.
单选题 绩效报告中通常不包括以下哪项?______
单选题About midway through the project,the project manager learns that most members of the project team do not review the weekly project updates.What should the project manager do?
单选题连续的降雨导致山洪暴发,道路被冲毁。如果未来一段时间内继续降雨,道路抢修需要20天;如果晴天,10天就可以修好;不过,从未来一段的天气预报情况推测,最有可能12天完成。则完成道路抢修的期望工期为______。
A.13天
B.15天
C.12天
D.14天
单选题In your construction project, the CPI is 1.30 and SPI is 0.85. What could be the potential reason?A) A critical resource went on sick leave for a long period of time, which had not been anticipated earlier.B) The Cost of raw materials required for construction increased 10%.C) You had not taken into account inflation rate.D) There was 4 days waiting time in the curing of cement, and work could not be done during that time.
单选题A resource histogram has all of the following characteristics EXCEPT:
单选题你所负责的一个为期3年的项目,刚刚进入收尾阶段,再过3周就可以宣布正式结束。这时,发现了一个已定义的重大缺陷。这很可能是以下哪个过程没有做好?( )A.识别风险B.规划风险管理C.监控风险D.应对风险
