单选题以下关于项目阶段和项目生命周期的说法都是正确的,除了______。
A.阶段结束点是对项目进行检查、评估和控制的当然时点
B.通常应该在重要可交付成果形成的时点,对项目分阶段
C.一个产品生命周期中通常包括多个项目生命周期
D.随着项目接近完工,项目变更的代价逐渐降低
单选题以下哪个不是定义活动过程的输出?( ) A.活动清单 B.活动属性 C.活动顺序 D.里程碑清单
单选题工作分解结构中的每一个要素应该是( )。 A.可交付成果 B.为完成可交付成果而进行的工作 C.表示活动的动词 D.可以是动词或名词,视具体情况而定
单选题The close project process is a part of which of the following project management knowledge areas?
单选题以下哪项不是干系人管理计划的内容?______
单选题The PM distributed a document to the stakeholders which
described the software to be developed, the functionality, the users it would
serve and the installation timeline. The document was an example of ______.
A. product scope
B. project scope
C. a combination of project and product scope
D. it was not complete enough to be either a product or a project scope
document
单选题Which knowledge area does the develop project charter belong to? A) Initiating. B) Project scope management. C) Project integration management. D) Project communication management.
单选题As a project manager, you realize the importance of team development for project human resource management. Team development helps in developing individual and group competencies to enhance project performance. All the following are tools and techniques for “Develop Project Team” EXCEPT ______ .
单选题下列关于项目阶段的说法,正确的是______。
A.项目阶段就是项目管理过程组
B.一个项目阶段的结束通常包括核准开始下一个阶段
C.在可交付成果被确认符合技术要求后,就可以结束该项目阶段
D.项目阶段的结束涉及可交付成果的交接
单选题在项目执行阶段的高峰期,某个关键活动的几个重要技术人员突然一起提出要离开项目,项目经理首先应该( )。 A.调整项目进度计划和进度基准 B.从非关键活动上抽调人员,确保关键活动的工期 C.实施风险应对措施 D.请求管理层的支持,以留住他们
单选题Key features of a project management office(PMO)generally include all of the following EXCEPT:
单选题验收已完成的可交付成果,是哪个过程的工作?( )。A.结束项目或阶段B.结束采购C.实施质量控制D.核实范围
单选题Which of the following statements is true about the WBS?
单选题Your department is currently working on four urgent projects when it is assigned a major new project. To staff the new project, one of the four urgents needs to be terminated. The benefit cost ratios(BCR)for the four projects are listed. Which would you select for termination?
单选题一位造价工程师为APT建筑公司在中国首个油田管道铺设项目估算成本。他没有得到任何详细的工程数据,应采取的费用估算方法是______。
单选题Reserve funds are set aside for use when ______.
A. an up-scope of the project requires additional funds to compensate the
initial budget
B. they are needed for the sporadic fluctuation in potential labor rates
when a union contract is under negotiation
C. anticipated problems have been identified but not completely
expected
D. a fund used when the client requests an up-score for the
project
单选题 项目经理邀请各主要干系人召开会议,对风险的概率和影响进行了评估。之后
单选题The critical path is established by calculating the following dates:
单选题在PDM图中,最常用的逻辑关系是______。
单选题以下哪个不是实施整体变更控制过程的工具与技术?______
A.专家判断
B.会议
C.变更控制工具
D.项目变更评审