单选题Ideally,communication between the project manager and the project team members should take place______. A) via daily status reports B) through approved documented forms C) by written and oral communication D) through the formal chain of command
单选题项目已经完成,已经将最终的可交付成果交给了客户,但是,客户拒绝对项目给出最终验收。这时,最重要的是项目经理______。
单选题 项目发起人授权项目经理起草项目章程,但是迟迟未能提供商业论证,其他文件均已提供
单选题Your project team identified six related projects with major dependencies on your deliverables. Some of these projects have a very similar scope and may overlap with your deliverables. In Light of this, which of the following should you be MOST concerned about? A) Scope change control. B) Scope verification. C) Risk response planning. D) Communications planning.
单选题Which is the most conservative of the work completion rules?
A. 50/50 Rule.
B. 0/100 Rule.
C. 20/80 Rule.
D. 100/100 Rule.
单选题In your project, there have been several changes in the cost and schedule estimates and the original estimating assumptions are no longer valid. What is the estimate at complete for your project? BAC=$300,000, AC=$100,000, EV=$150,000, CPI=$1.2, ETC=$120,000.
单选题 以下哪个不是管理干系人期望过程的输入?______
单选题What is the purpose of the contingency money in a cost estimate?
A. Provides money to cover uncertainties in the estimate within the defined
scope and schedule.
B. Money to cover changes in scope.
C. Money to cover unforeseen natural disasters.
D. A and C.
单选题 你所负责的项目涉及向多个供应商采购产品,然后加以组合,形成最终的项目产品。项目进行了一半之后
单选题 作为项目经理获取、存储和向干系人发布项目成本、进度和绩效信息的标准工具
单选题你所负责的项目,其总预算为12000美元,需要在6周内建造100个产品。你刚刚开始第4周。到目前为止,你花了4000美元成功地建造了50个产品。在这种情况下,成本偏差说明了什么?( )A.项目正在110%地按照预期进度计划执行B.项目低于预算2000美元C.项目在预算内D.项目每花费1美元做了2美元的工作
单选题在管理干系人参与过程中,一些老问题被解决,新问题又出现。应该最先动态更新以下哪个文件?______
单选题One of the fundamental tenets of modern quality management is:
单选题采购谈判是以下哪个过程的工具与技术?______
单选题以下哪个是外部风险的例子?
单选题In what way does free float differ from total float? A) Free float is the amount of total float that does not affect the end date, whereas total float is the accumulated amount of free float. B) There is no difference-the two terms are functionally equivalent. C) Free float is the amount of time that a schedule activity can be delayed without delaying the early start of any immediately following schedule activities, whereas total float is concerned with delays that do not affect the project finish date. D) An activity's free float is calculated by subtracting its total float from the critical path's total float.
单选题Output from the activity resource estimating process includes ______ .
单选题Rebaselining may be required in cost control when ______ .
单选题以下关于项目生命周期的说法,正确的是( )。A.通常相互交叉而有时又按顺序排列的各阶段的集合B.指启动、规划、执行、监控和收尾等五个过程组的集合C.不同的组织通常采用阶段名称相同、阶段数量相同的项目生命周期D.通常按顺序排列但也可能相互交叉的各阶段的集合
单选题项目发起人是项目最重要的干系人之一,他的需求满足程度将对项目产生很大的影响,作为项目经理,你应该高度重视与发起人的沟通。目前处于项目启动阶段,如果发起人问你:“现在预计全部工作的成本是多少?”由于你使用挣值管理技术,你应当计算______。