单选题The cost management plan has all of the following characteristics EXCEPT:A) It is based on the project cost estimates, and is separate from the project plan.B) Can establish variance thresholds for costs or other indicators.C) May be formal or informal, highly detailed or broadly framed.D) Documents the cost management processes and their associated tools and techniques.
单选题以下哪项是项目的配置管理活动?( ) A.识别和记录项目的重要技术参数 B.识别和记录项目的主要风险 C.为项目活动配置所需的人力资源 D.为项目活动配置各种人力和非人力资源
单选题During a project the scope of a product purchased on a cost reimbursable contract has increased. In the contract the fee to cover the contractor's indirect costs and allow a profit is calculated as 20% of the direct costs. What is most likely to be true? A) The contractor's indirect costs will increase and the customer's payment for them will increase, too. B) The contractor's indirect costs will increase but the eLlstomer's payment for them will not increase. C) Neither the contractor's indirect costs nor the customer's payment for them will increase. D) The contractor's indirect costs will not increase but the customer's payment for them will increase.
单选题项目经理经常使用哪种沟通方法来发布项目绩效报告?______
单选题A project team is in the design stage of a new mountain bike prototype. The team is in the process of identifying which type of frame and material will provide high performance at a low cost. Which of the following is the MOST likely technique used to determine these variables?
单选题以下各项都是风险减轻的例子,除了______。
单选题某个项目管理过程之所以被列入规划过程组,是因为______。
A.它不可能在启动阶段使用
B.它主要是在规划阶段使用
C.它不可能在执行阶段使用
D.它不适合列入其他过程组
单选题你所管理的项目将需要在多个物理地点开展,涉及的风险比较多。你从公司的组织过程资产中了解到,过去类似项目的风险管理工作比较混乱。你想要在本项目上改变这种局面。为了有效地管理本项目的风险,你首先应该( )。 A.识别潜在的风险及影响 B.指定专门人员负责风险管理 C.编制风险管理计划 D.编制风险登记册
单选题The work breakdown structure is an excellent tool for objective control and evaluation. Which of the following is generally not validated through the WBS?A) Time, schedule, and cost.B) Management coordination and organizational structuring.C) Risk and impact of decision—making.D) Quality of the work.
单选题The type of contract where the buyer incurs opportunity cost but little or no additional cost risk is called______. A) fixed-price with incentive B) firm-fixed-price C) fixed-price with economic price adjustment D) fixed-price with right of renewal
单选题项目经理应该使用下列哪种方法帮助团队成员克服工作技能不足?______
A.心理辅导
B.教练技术
C.建立信任
D.充分激励
单选题以下哪个是结束项目或阶段过程的输入?( )A.完成的可交付成果B.验收的可交付成果C.确认的可交付成果D.最终的可交付成果
单选题你是人力资源管理专家,最近被分派到某项目团队,制定基于团队的奖励和认可制度,其他团队成员也就职于人力资源部门。项目章程应由______发出。
单选题 管理层很不满意你的项目的进展情况。项目开工2年以来,发生了几件意外的负面事件,使项目绩效持续恶化
单选题项目经理要求团队成员从活动开始计算项目成本,这种估算技术是______。
单选题在合同执行过程中,你收到卖方提出的一项索赔,要求你为额外增加的测试工作付款。解决合同执行过程中的争议和索赔,应该采用什么方法?( )A.调解B.谈判C.仲裁D.ADR
单选题You are trying to determine what cost and schedule trade-off will be most appropriate for your project. You have the option to select either a more experienced person at $120 per hour who can do the task in 45 days or a less experienced person at $80 per hour who can do the same task in 65 days. A tool you can use to facilitate making the decision is ______ .
单选题以下哪个关于项目生命周期的说法是正确的?( )A.所有项目的项目生命周期都包括启动、规划、执行、监控和收尾等5个阶段B.干系人的职责和作用,在整个项目生命周期中通常保持不变C.随着项目接近完工,项目失败的可能性降低,负面风险的影响也降低D.即便同一类项目,也可以有不同的项目生命周期阶段划分
单选题下列各项都是合同变更控制系统的组成部分,除了______。
单选题When should lessons learned be organized?