单选题在项目收尾阶段,需要收集和归档各种项目计划、文件和其他资料,以便满足下列所有需要,除了______。
A.积累项目知识,供以后项目使用
B.遵守法律法规的要求
C.供可能的外部审计使用
D.对项目团队成员进行认可和奖励
单选题质量保证工作属于质量成本中的那一类工作?______
A.兼具一致性工作和非一致性工作的特性
B.一致性工作
C.非一致性工作
D.既不属于一致性工作,也不属于非一致性工作
单选题以下哪项最有助于降低缺陷率?______
A.改进过程
B.测试成品
C.定义质量标准
D.制定进度基准
单选题你通过电子邮件向客户发送项目设计的技术规范文件。但是,客户抱怨打不开文件,并因此不能按时进行审查。造成这种情况的原凶是( )。 A.干系人管理不当B.沟通规划不当 C.信息发布错误 D.绩效报告错误
单选题进行项目沟通需求分析,旨在确定______。
单选题你负责的项目已经完成70%的进度,但成本与基准有重大偏差,且已超出可恢复的范围。根据成本偏差情况,团队提出了成本基准变更请求,并已取得变更控制委员会的批准。作为这个变更的结果,以下所有文件都需要相应更新,除了______。
A.范围基准
B.完工尚需绩效指数
C.项目管理计划
D.组织过程资产
单选题可交付成果必须具备的特性、功能和特征属于下列哪类需求?______
A.业务需求
B.干系人需求
C.解决方案需求
D.项目需求
单选题 发起人参与了项目可交付成果的正式验收。收尾阶段进行移交时,发起人表示不会接收项目的可交付成果
单选题 预期货币价值分析经常用哪种图形来表示?______
单选题All of the following are inputs to risk identification EXCEPT______.
单选题An example of scope verification is ______.
A. review the performance of an installed software module
B. managing changes to the project schedule
C. decomposing the WBS to a work package level
D. performing a benefit/cost analysis to determine if we should proceed with
the project
单选题The following are the internal rate of return(IRR)for different projects.Project A:5%,project B:25%,project C:30%,project D:99%.Which is the best project?
单选题应当基于哪类基准来评价项目的成功?______
A.正确的基准
B.最新的基准
C.原有的基准
D.批准的基准
单选题Controlling occurs ______. A) on a continual basis throughout the project B) at the end of each phase of the project life cycle to assess its success in meeting project objectives C) at the end of each planning process D) on a continual basis throughout the executing process and as needed in the other process
单选题None of the people on your 15 person project team have worked together before, and it really shows. The team cannot seem to get past the storming stage: each meeting is characterized by disagreements, debates, and long-winded expositions some of the more verbose members of the group. Everyone seems to speak a different “language” even though they are all from the same country. Conflicts are rampant. You need to get this situation under control quickly. Therefore, the first action you should take is to______. A) hold periodic group meetings B) use a group facilitator at the next meeting C) perform careful project planning D) enforce strict rules about meeting behavior
单选题假设估计幅度的两端是平均数的正负3σ,以下哪个范围估计的风险最低?
单选题你得到了如下关于活动、逻辑关系和持续时间的信息:a是开始活动,工期3天;b是开始活动,工期是7天;c的紧前活动是a(开始到开始关系),工期4天;d的紧前活动是a和b,工期1天;e的紧前活动是c和d,工期6天;f的紧前活动是d,工期5天;g为结束活动,其紧前活动是e和f,工期2天。位于关键路径上的活动有( )。A.b-d-f-gB.d-e-gC.a-c-e-gD.b-d-e-g
单选题 项目的可交付成果已完成,并通过了内部的质量检验。团队成员建议举办一个移交仪式
单选题 巴伯负责某软件开发项目中的某个工作包,他曾经与小组中的两个成员认真讨论过该如何完成这个工作包
单选题项目所必需的各专家处于项目所在城市以外的几个不同城市,而专家们的频繁旅行将导致成本严重超支。在组建项目团队时,项目经理应该______。
A.重新招募新的专家
B.考虑减少专家旅行的次数
C.考虑组建虚拟团队
D.直接向管理层求助