坡地超高层建筑的桩基础及阶梯式箱形承台设计 被引量:1

Design of pile foundation and stepped box-type bearing platform for super high-rise buildings on sloping land
下载PDF
导出
摘要 某典型坡地项目,地下车库一侧全埋,一侧开敞,两侧高差48~62m。结合场地高差的特点,为减少对现状地形的破坏,确保坡地桩基础受力的整体性,基础顶采用了阶梯式箱形承台,并通过有限元分析验证了阶梯式箱形承台与桩基整体受力形式的合理性。对塔楼整体抗倾覆、滑移和基础抗剪的验算,确保坡地基础埋深不足下的结构安全。在保证塔楼结构安全的前提下,主体结构应尽量减少其对边坡稳定的不利影响。关于坡地基础的设计方法可供类似项目参考。 In a typical sloping land project, the underground garage is fully buried on one side and exposed on the other side. The elevation difference between the two sides is 48~63m. Combined with the characteristics of the site, to reduce the damage to the existing terrain and ensure the integral force transfer of the pile foundation on the slope, a stepped box-type bearing platform is used for the top of the foundation. The rationality of the force transfer mechanism of the pile foundation is demonstrated by using finite element analysis. Through the review of the integral capacity of anti-overturning and sliding and foundation shear resistance of the tower, the structural safety of the sloping foundation with insufficient burial depth is ensured. On the premise of satisfying the safety of the tower, the main structure should minimize its adverse effects on slope stability. The design method for sloping foundations can be used as a reference for similar projects.
作者 方飞虎 林超伟 吴昀泽 王紫旻 沈忠伟 沈文赫 FANG Feihu;LIN Chaowei;WU Yunze;WANG Zimin;SHEN Zhongwei;SHEN Wenhe(PT International Design Consultants(Shenzhen)Co.,Ltd.,Shenzhen 518031,China;Shenzhen PT Lansen International Architecture Design Co.,Ltd.,Shenzhen 518031,China;Shenzhen Metro Property Development Group Co.,Ltd.,Shenzhen 518040,China)
出处 《建筑结构》 CSCD 北大核心 2022年第S02期2080-2085,共6页 Building Structure
关键词 坡地 阶梯式箱形承台 埋深不足 边坡稳定 sloping land stepped box-type bearing platform insufficient burial depth slope stability
  • 相关文献

参考文献1

二级参考文献13

共引文献22

同被引文献14

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部