摘要 在供应链的物流管理思想[1]基础上,为实现钢铁企业内部能源的优化分配,根据RLP(resource level problem)与RCPSP(resource-constrained project scheduling problem)的相似之处和自身的特点以及针对实际问题结构和特征,提出资源有限的弱资源水平问题这一新概念;设计了一种求解弱RLP(soft resourcelevel problem)的方法;最后举例进行了验证.
作者 李强 池宏
出处 《中国管理科学》 CSSCI 2003年第z1期61-65,共5页 Chinese Journal of Management Science
  • 相关文献

参考文献13

  • 1[1]Bertazzi L.and Speranza M.G. Minimizing logistics costs in multistage supply chains [J]. Naval Research Logistics, 1999,46(4) :399- 417.
  • 2[2]Lee H L,Padmanabhan V,Whang S.The bullwhip effect in supply chain[J] .Sloan Management Review, 1997,38(4):93- 102.
  • 3[3]Towill D R.Industrial dynamics modeling of supply chain[J] .International Journal of Physical Distribution&Logistics Management, 1996, 26(2) :23 - 24.
  • 4[4]Fisher,Marshall L.What is the right supply chain for your product[J]. Harvard Business Review, 1997,2:105 - 116.
  • 5万杰,李敏强,寇纪淞.供应链中分配机制对牛鞭效应的影响研究[J].系统工程学报,2002,17(4):340-348. 被引量:27
  • 6[6]Bandelloni M, TucciM, RinaldiR. Optimal resource leveling using nonserial dynamic programming[J] .European Journal of operational Research, 1994,78:162- 177.
  • 7[7]Younis M A, Saad B.Optimal resource leveling of multi- resource projects[ J ]. Computers and Industrial Engineering, 1996,31:1 - 4.
  • 8[8]Leachman R C.Multiple resource levelling in construction systems through variation of activity intensities [ J ] .Naval Research logistics Quarterly, 1983,30:187 - 198.
  • 9[9]Neumann K, Zimmermann J. Resourcs levelling for projects with schedule-dependent time windows[J] .European Journal of Operational Research, 1999,117:591 - 605.
  • 10刘士新,王梦光.一种求解工程调度中资源水平问题的遗传算法[J].系统工程理论与实践,2001,21(4):24-26. 被引量:10

二级参考文献24

  • 1王梦光,刘士新.资源受限工程调度问题的最新发展[J].控制与决策,1996,11(A01):105-112. 被引量:11
  • 2[1]Mo¨hring R H. Minimizing costs of resource requirements in project networks subject to a fixed completion time[J]. Operations Research, 1984, 32: 89-120.
  • 3[2]Bandelloni M, Tucci M, Rinaldi R. Optimal resource levelling using non-serial dynamic programming[J]. European Journal of Operational Research, 1994, 78: 162-177.
  • 4[3]Younis M A, Saad B. Optimal resource levelling of multi-resource projects[J]. Computers and Industrial Engineering, 1996, 31: 1-4.
  • 5[4]Leachman R C. Multiple resource levelling in construction systems through variation of activity intensities[J]. Naval Research Logistics Quarterly, 1983, 30: 187-198.
  • 6[5]Seibert J E, Evans G W. Time-constrained resource levelling[J]. Journal of Construction Engineering and Management, 1991, 117: 503-520.
  • 7[6]Demeulemeester E. Minimizing resource availability costs in time-limited project networks[J]. Management Science, 1995, 41(10): 1590-1598.
  • 8[7]Demeulemeester E, Herroelen W. A branch-and-bound procedure for the multiple resource-constrained project scheduling problem[J]. Management Science, 1992, 38(12): 1803-1818.
  • 9[8]Neumann K, Zimmermann J. Resource levelling for projects with schedule-dependent time windows[J]. European Journal of Operational Research, 1999, 117: 591-605.
  • 10[9]Kolisch R. Serial and parallel resource-constrained project scheduling methods revisited: theory and computation[J]. European Journal of Operational Research, 1996, 90: 320-333.

共引文献45