摘要
应用海拉瓦技术 ,改变了送电线路路径优化作业模式 ,提高了设计质量和效率 ,缩短线路长度 1%~2 % ,有效地减少了房屋拆迁和林木砍伐 ,保护了生态环境 。
Application of Hailawa technique has changed the optimized operation mode for the routine of transmission lines, increased the design quality and efficiency, reduced the length of the lines about 1%~2% and decreased the removal of houses and fell of trees so as to protect the ecological environment and offer a basis for further change of transmission line design.
出处
《电力建设》
北大核心
2002年第11期81-84,共4页
Electric Power Construction
关键词
全数字化测量系统
路径优化
海拉瓦技术
digital measuring system
optimization of line routine
Helava technique