为了解RCC的一些热学特性和在RCC施工中应重视的环节,以及通过合理调度冷却通水工作探讨高温季节RCC施工的可能性,对RCC的绝热温升、绝热情况下不同龄期坝内平均温度及初期冷却通水效果进行了计算分析。
For the purpose of knowing the thermal characteristics of RCC and the important links in construction period, and finding out the possibility of RCC construction in high temperature season, the heat insulated temperature ascent of RCC, the mean temperature of different age concrete in the cofferdam under heat insulated condition, and the cooling effect in early days are analysed.
出处
《湖北水力发电》
2002年第2期47-51,共5页
Hubei Water Power
关键词
RCC施工
高温季节
温度控制
RCC, high temperature season, temperature control