乐昌峡水电站溢流坝消能方案试验研究 被引量:4

Research on Energy Dissipation Scheme of Overflow Dam at Lechangxia Hydropower Station
下载PDF
导出
摘要 乐昌峡水电站溢流坝具有泄流落差和单宽流量较大、下游河道狭窄等特点,溢流坝的消能问题较突出。通过水工模型试验研究,对溢流坝挑流消能工布置和体型进行比较,推荐溢流坝采用反弧段一体的扩散式梯形差动式挑流鼻坎的消能方案,妥善解决了溢流坝消能问题。 The flood-releasing energy dissipation problem of the overflow dam at Lechangxia hydropower station is outstanding as it has large water head drop and the discharge per unit width of the dam is large,and moreover,the downstream is narrower.Based on hydraulic model test,the deflecting energy dissipator layout and configuration of the overflow dam are compared and hence energy dissipation problem of the overflow dam is solved properly in this paper by recommending diffusedal trapezoid differential flip bucket with overall ogee.
出处 《水利科技与经济》 2012年第10期50-52,65,共4页 Water Conservancy Science and Technology and Economy
关键词 溢流坝 挑流鼻坎 消能 模型试验 乐昌峡水电站 overflow dam bucket energy dissipation model test Lechangxia hydropower station
  • 相关文献

参考文献1

二级参考文献2

  • 1中华人民共和国水利部.S1319-2005,混凝土重力坝设计规范[S].北京:中国水利水电出版社,2005.
  • 2华东水利学院.水工设计手册(第6卷)[K].北京:水利电力出版社,1982.

共引文献10

同被引文献31

引证文献4

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部