摘要
以实际工程为例,详细介绍单轨吊车用于超高层单元式建筑幕墙安装施工技术,该技术可以不需等待建筑主体结构完成就从下往上地进行单元式建筑幕墙施工,与主体结构平行、同步组织施工,加快工程施工进度,且施工便捷,工效高,可操作性强及施工安全有保证,并可反复装拆移动使用,设备成本低。
In this paper,taking the actual project as the example,introduces the monorail crane for installation and construction technology of super high-rise unit building curtain wall,this technology can not wait for the construction of the main structure completed will be from the bottom to the top of the unit type curtain wall construction,and the main structure of parallel,synchronous organization construction, quicken the construction progress and construction convenience,high efficiency,be assured,strong operation and construction safety,and can be repeatedly disassembled for mobile use,low cost of equipment.
出处
《广东土木与建筑》
2013年第12期20-22,44,共4页
Guangdong Architecture Civil Engineering
关键词
超高层建筑
单元式建筑幕墙
单轨吊车
分段安装
ultra-high-rise buildings
unit building curtain wall
monorail crane
section installation