摘要 750kV开关设备现场交流耐压车载试验平台通过优化设计研究,包括平台整体设计、电场分布仿真计算、轴荷分配与质心稳定性校核等,将750kV成套变频串联谐振试验装置和辅助系统集成于车上,无需依赖外部吊装设备,自动化控制水平高,接线方便。通过将国内最高电压等级的750kV整车耐压试验平台成功应用到某±800kV特高压换流站,工作效率至少提高了5倍。 By optimization designing,including the overall design,calculation of the electric field,axle load distribution and centroid stability check,etc,750 kV switchgear live AC voltage vehicle test platform integrates 750 kV complete series resonant frequency test equipment and auxiliary systems in a car.The platform needn' t relying on external lifting equipment,which has high level of automation and easy to wire.The 750 kV voltage test vehicle platform which has the highest voltage level has successfully applied to a±800kV HVDC converter station,the work efficiency is increased at least five times.
出处 《湖北电力》 2014年第6期25-29,33,共6页 Hubei Electric Power
关键词 车载试验平台 现场交流耐压试验 电场分布计算 轴荷分配 质心稳定性 安全价值分析 vehicle test platform live AC voltage test calculate the electric field distribution axle load distribution centroid stability security value analysis
  • 相关文献

参考文献11

二级参考文献31

  • 1张占,陈家强,娄东升,张亮,佘磊.浅评电力变压器的预防性试验[J].电气试验,2009,2(1):14-17. 被引量:17
  • 2连逊章,王中汉,郑维邦.变频谐振装置耐压试验等效性研究[J].高电压技术,1995,21(1):26-28. 被引量:4
  • 3华北电力科学研究院有限责任公司.现场绝缘试验实施导则(DL/T474.1-DL/T474.5-2006)[S].北京:中国电力出版社,2006.
  • 4国电北京电力建设研究所,安徽省电力科学研究院,东北电业管理局第二工程公司,等.电气装置安装工程电气设备交接试验标准(GB50150-2006)[EB/OL]. http ://www. dianli.com/bbs/d/55/731. html,2007-07-24.
  • 5电力设备预防性试验规程,Q/CSG 10007-2004[S].
  • 6[1]A. Diessner, G. F. Luxa, W. Mosca, A. Pigini. High voltage Testing of GIS Insulated Substation on Site[R]. CIGRE session 1986 Report 33-06.
  • 7[2]CIGRE WG 33/23-12. Insulation Coordination of GIS: Return of Experience, on Site Tests and Diagnostic Techniqures[R]. August,1996.
  • 8[3]CIGRE WG 33/23-12. Insulation Co-ordination of GIS:Return of Experience, on Site Tests and Diagnostic Techniqures[R].Electro,No.176,1998.
  • 9[4]IEC 517. Gas Insulated, Metal Enclosed Switchgear for 7.2 kV and above[S].
  • 10[6]R. Feger, K.Feser. Empfindenlichheit Verschiedener Teilentladungs-Messverfahren bei der Voe-Ort-Pruefung von Gasisoliertn Schaltanlagen. HIGHVOLT KOLLOQUIUM, 1999.

共引文献94

同被引文献26

引证文献3

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部