摘要
基于非恒定流理论,采用一维与二维结合的数学模型全过程、全区域地模拟岭澳核电站岭下水库溃坝洪水的下泄过程及向下游的演进过程,分析了溃坝洪水对厂址及一期核岛的影响。
Based on the theory of unsteady flow,a mathematic model combining one dimension with two dimension was employed to simulate the release of dam_bursting flood and its advance towards downstream in an all_round way for Lingxia Reservoir of Lingao Neclear Power Plant.The paper analized the influences of dam_bursting flood on the plant site and stage I nuclear island.
出处
《人民珠江》
2004年第4期15-17,共3页
Pearl River
关键词
核电站
水库
溃坝洪水
数值模拟
nuclear power plant
reservoir
dam_bursting flood
numerical simulation