介绍一种双地线 10kV三芯交联电力电缆终端头安装工艺 ,并提出了对《铁路电力施工规范》、《铁路电力设备安装标准》的修订意见。
The paper diccussed the fixing technics of the terminal head of 3 core cross linking 10?kV power cable,and put forward the revision advice on Railway Electric Power Construction Specification and Mounting Standard of Railway Electric Power Equipment.
出处
《铁道机车车辆》
2004年第6期61-63,共3页
Railway Locomotive & Car
关键词
安装工艺
规范
改进意见