摘要
南京赛虹桥交通枢纽工程,地处秦淮河,有大量的涉水地下及水中工程。受城市污水的影响,对工程的混凝土需进行三级防腐处理。文章介绍选用耐腐蚀外加剂UC-10掺加于混凝土中,经耐腐蚀性能试验和对施工质量抽检结果,混凝土性能全部合格,效果比较理想。
With many underground fording works and underwater works, the Nanjing Saihong Bridge Traffic Hub Project is located at Qinhuai River. Because of the affection of urban sewage, the concrete of the project should be treated in grade-3 corrosion-resisting treatment and the admixture UC-10 is selected to add into the concrete. The results of corrosion-resisting performance test and construction quality inspection show that all the concrete performances are qualified.
出处
《中国市政工程》
2004年第6期31-32,共2页
China Municipal Engineering