摘要
随着火电空冷机组在工程中大量的采用, 通常主厂房 A列外电气设备的布置由于受空冷装置的影响, 引起了电气设备的布置和选型的变化, 与大家共同探讨解决办法。
A large amount of coal-fired air-cooling units are utilized in projects nowadays, usually the arrangement & type selection of electrical equipment outside the main building Row A shall be modified in accordance with the arrangement of air-cooling equipment. This paper is to seek the solutions for power plant.
出处
《电力勘测设计》
2005年第1期50-51,59,共3页
Electric Power Survey & Design
关键词
空冷平台
变压器
热交换管束
污秽等级
air-cooling platform
transformer
heat exchanger tubes
dirtiness class