基于浮动工时率的资源均衡问题研究 被引量:3

Research on resource leveling based on float rate
下载PDF
导出
摘要 引入浮动工时率的概念 ,提出了结合浮动工时率和网络计划工序拓扑排序的一种新的编码解码方法 .与一般的网络计划资源均衡中应用的遗传算法相比 ,可以避免遗传操作———初始化种群、交叉、变异中可能出现的一些违反网络计划工序间逻辑关系的非法个体的情况 ,具有简单、实用的特点 ,可在网络计划优化问题中推广 . The concept of float rate was introduced. Integrating float rate with the toposorting of activities in network scheduling, a new method of coding and decoding was presented. Compared with GA applied to resource leveling, this method can avoid generating invalid individuals in GA operations, such as initializing generation, crossovering and mutation. This method was more simple and suitable than other methods. It can be widely used in network scheduling optimization.
出处 《华中科技大学学报(自然科学版)》 EI CAS CSCD 北大核心 2003年第3期78-80,共3页 Journal of Huazhong University of Science and Technology(Natural Science Edition)
关键词 资源均衡 遗传算法 浮动工时率 拓扑排序 resource leveling GA float rate toposorting
  • 相关文献

参考文献4

二级参考文献9

共引文献47

同被引文献15

  • 1Hiyassat M A S.Applying Modified Minimum Moment Method to Multiple Resource Leveling[J].Journal of Construction Engineering and Management,2001,127 (3):192-198.
  • 2Rudolph G.Convergence Analysis of Canonical Genetic Algorithms[J].IEEE Trans.on Neural Networks,1994,5(1):96-101.
  • 3杜黎.网络计划的资源优化和平衡[C].中国运筹学会.中国运筹学会第六届学术交流会论文集,中国运筹学会第六届学术交流会,湖南长沙,2000年10月10日-15日,香港:Global-Link出版社,2000:535-541.
  • 4Weng-Tat Chan, David K. H. Chua, Govindan Kannan. Construction resource scheduling with genetic algorithms [J]. Jounal of Construction Engineering and Management, 1996, 122 (2):125 - 132.
  • 5Kris G. Mattila, Dulcy M. Abraham. Resource Leveling of Linear Schedules Using Integer Linear Programming[J]. Journal of Construction Engineering and Management, 1998, 124 (3) :232 - 244.
  • 6Sou-Sen Leu, Chung-Huei Yang. GA-Based Multicriteria Optimal Model for Construction Scheduling [ J ]. Journal of Construction Engineering and Management, 1999,125 (6) :420 - 427.
  • 7Zne-Jung Lee, Chou-Yuan Lee. A hybrid search algorithm with heuristics for resource allocation problem [ J ]. Information Sciences, 2005,173 : 155 - 167.
  • 8Chan W T,Chua D K H,Kannan G.Construction resource scheduling with genetic algorithms[J].Jounal of Construction Engineering and Management, 1996,122(2): 125-132.
  • 9Leu S S,Yang C H.GA-based multicriteria optimal model for construction scheduling[J].Jounal of Construction Engineering and Management, 1999,125 ( 6 ) : 420-427.
  • 10Son J,Mattila K G.Binary resource leveling model activity splitting allowed[J].Joumal of Construction Engineering and Management, 2004,115 ( 6 ) : 887 -894.

引证文献3

二级引证文献14

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部