摘要 可中断负荷管理是电力市场环境下需求侧管理的重要组成部分,与电力系统安全经济运行密切相关。该文讨论了可中断负荷合同的内容和相关市场组织形式;利用停运表得到考虑负荷波动情况下的系统缺额容量以及采用需求侧报价来反映用户可接受的停电补偿。给出可中断负荷的最优购买模型,模型以购买费用最小作为目标函数,包括停电持续时间和停电总次数等约束。参照机组检修的思路,给出安排可中断负荷的基本原则并采用相应算法求解。实际系统算例表明该模型的有效性。 Interruptible load management (ILM) is an important part of Demand Side Management (DSM) in power market. This paper discusses the contents and implementation processes of the interruptible load contract. Demand side bidding (DSB) is utilized to embody the compensation cost for the large users. Considering the load fluctuation, we use the capacity outage table to obtain the expectation value of power not served. Then the paper presents the optimal purchase model of interruptible load. Similar to the maintenance schedule method, a merit order method is employed to solve the problem. Case studies for a real power system demonstrate usefulness of the proposed model.
出处 《中国电机工程学报》 EI CSCD 北大核心 2005年第9期11-16,共6页 Proceedings of the CSEE
基金 国家自然科学基金重点项目(59937150) 国家973重点项目(2004CB217905)~~
  • 相关文献

参考文献12

二级参考文献43

  • 1曹世光,杨以涵,于尔铿.缺电成本及其估计方法[J].电网技术,1996,20(11):72-74. 被引量:34
  • 2水利电力部.电力系统技术导则[M].北京:水利电力出版社,1984..
  • 3Wolak F A. An empirical analysis of the impact of hedge contracts on bidding behavior in a competitive electricity market[J]. International Economic Journal, 2000, 14: 1-40.
  • 4Green R J. The electricity contract market in England and Wales [J]. Journal of Industrial Economics, 1999, 47(1): 107-124.
  • 5KIRSCHEN D S. Demand-side view of electricity markets[J]. IEEE Trans. on Power Systems, 2003,18(2):520-527.
  • 6MALIK A S. Simulation of DSM resources as generating units in probabilistic production costing framework [J].IEEE Trans. on Power Systems, 1998,13(4) :460-465.
  • 7TOLLEFSON G,BILLINTON R,WACKER G. Comprehensive bibliography on reliability worth and electrical service consumer interruption costs-1980-90 [J]. IEEE Trans. on Power Systems, 1994,9(4): 1508-1514.
  • 8CHOI S B,KIM D K,JEONG S H,et al. Evaluation of the customer interruption cost taking into consideration macro economic approach in Korea [A]. Proceedings of International Conference on Power System Technology[C]. Xi'an, China: PowerCon, 2002. 2358-2362.
  • 9MOK Y L,CHUNG T S. Prediction of domestic,industrial and commercial interruption costs by relational approach[A]. Proceedings of Fourth International Conference on Advances in Power System Control,Operation and Management[C]. Hong Kong: APSCOM, 1997. 209-
  • 10KARIUKI K K,ALLAN R N. Factors affecting customer outage costs due to electric service interruptions[J]. IEE Proceedings on Generation,Transmission and Distri.bution, 1996,143(6):521-528.

共引文献152

同被引文献1203

引证文献115

二级引证文献1433

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部