摘要
为了改善中心城水厂的反应、沉淀池穿孔排泥管的排泥效果,对原排泥管进行了复核计算,并重新布孔,改造后提高了排泥效率,减少了自用水量。
In order to improve the sludge discharge from perforated pipe of reaction and sedimentation tank in Central Waterworks, the computation for the existing sludge discharge pipe was checked and the holes were rearranged. After renovation, the efficiency of sludge discharge was increased and the water wasted from sludge discharge was reduced as well.
出处
《中国给水排水》
CAS
CSCD
北大核心
2005年第8期80-81,共2页
China Water & Wastewater
关键词
自来水厂
穿孔排泥管
布孔
waterworks
perforated sludge discharge pipe
hole arrangement