网络计划资源均衡模型的改进及其应用 被引量:9

Improved Network-Planning-Based Resources Leveling Model and Its Application
下载PDF
导出
摘要 针对现有资源均衡模型的不足,提出一种改进的资源均衡模型.即选择资源过度分配最严重的时段作为优先调整时段;在调整工序时不但考虑工序的时间属性,还综合考虑其经济属性和施工属性;在确定可调整量时, 全面考虑工序的限定和制约因素,摒除其中的虚假时差成分.并用Visual C++语言编制了相应程序.最后,通过一个例子阐明了改进模型的特点. An improved network-planning-based resources leveling model is presented. Firstly, the period of time, during which resources are most excessively allocated, is chosen for resource leveling. Then activity is adjusted considering not only job's time attribute but also the economic and constructional nature. When adjust- able amount for a job is calculated, limits on the activity and some constraints are analyzed to eliminate job's virtual float. Furthermore, an improved resource leveling model is built to solve the problem and some concrete operational steps are given. The function of the improved model is programmed in Visual C + + language. Finally, a case study is carried out to demonstrate the applicability and effectiveness of the proposed model.
出处 《天津大学学报》 EI CAS CSCD 北大核心 2006年第2期250-255,共6页 Journal of Tianjin University(Science and Technology)
关键词 网络计划 资源均衡 工序 调整 时差 network planning resources leveling activity adjustment float
  • 相关文献

参考文献7

  • 1Davis E W,Patterson J H.A comparison of heuristic and optimum solutions in resource-constrained project scheduling[J].Management Science,1975,21(8):944-955.
  • 2Gordon J,Tulip A.Resource scheduling [ J ].International Journal of Project Management,1997,15(6):359-370.
  • 3Chelaka M,Abeyasinghe L,Greenwood D J.An efficient method for scheduling construction projects with resource constraints[J].International Journal of Project Management,2001,19(1):29-45.
  • 4Brucker P,Drexl A.Resource-constrained project scheduling notation,classification,models,and methods[J].European Journal of Operational Research,1999,112(1):3-41.
  • 5王仁超,褚春超,李喆,李名川.考虑工序间两类依赖关系的网络计划方法[J].天津大学学报(自然科学与工程技术版),2004,37(4):312-317. 被引量:11
  • 6Raz Tzvi,Marshall B.Effect of resource constraints on float calculations in project networks[J].International Journal of Project Management,1996,14(4):241-248.
  • 7Mohammed A,Salem Hiyassat.Applying modified minimum moment method to multiple resource leveling[J].Journal of Construction Engineering and Management,2001,127 (3):192-198.

二级参考文献2

共引文献10

同被引文献89

引证文献9

二级引证文献36

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部